6
– Commissioning of the IDEO
In order to commissioning your installation, it is necessary to follow the following process:
1. Check that all the installation components are in their proper place and connected:
•
Air intake make with insulated duct and properly connected (do not use air intake fitted
with protection guard),
•
Supply discharge and extraction ducts make as insulated ducts and properly connected,
•
Supply and extract values connected,
•
Air volume regulators fitted in the correct direction (if installed),
•
Air discharge executed in insulated duct and connected to the exterior (use a roof
ventilation terminal or a discharge outlet without protection guard),
•
Very tight flexible insulated ducts and long-radius bends (if installed),
•
Check that the spigots not used on the plenums are properly sealed off (if installed),
•
Condensate exhaust properly connected (siphon),
•
Check that all the connections are really airtight (on the, IDEO on plenums and on plugs)
•
Check the calibration of the electrical protector (3A)
2. Switch on the IDEO,
3. Set the time and the day,
4. Set the minimum and maximum airflow,
5. Choice of mode (auto 1, auto 2, manual or boost),
6. Select the bypass mode,
7. Set the type of external switch (if installed), “NO” for Normally Open and “NC” for Normally Closed
(see Chapter 6.1),
8. Check the transmission/reception level between the remote control and the IDEO. In the case of a
low level, it is possible to install a more powerful antenna. In the case of the presence of other
devices functioning by radio frequency, there may be interference problems which can affect the
IDEO's proper functioning. If you notice instances of irregular functioning, we advise you to
change the communication channel (see Chapter 7)
9. Make the test pressure drop of the system (see Section 6.1).
An unsatisfactory test result (I02) may be caused by the following:
•
The installation is complex with too many pressure drops. In this case, you must
improve the ductwork by limiting the number of bends and excessive lengths. Use
the long-radius bends.
•
The installation is make with flexible ducts. In this case, check that the ducts are
really stretch and/or no ducts are crushed.
Summary of Contents for IDEO2 325 Ecowatt
Page 1: ...2 IDEO 325 Ecowatt Installation manual and comissioning EN ...
Page 8: ...3 3 Hubcap for ducts Optional 4 x 4 x ...
Page 22: ......
Page 23: ......