Configuring the Inline Meter Connection using the SetApp Device Manager
To configure the inline meter for Energy Net communication using the SetApp
Device Manager:
1. From the SetApp Commissioning menu, select
Device Manager
.
2. From the Device Manager's New Devices page, select
Inline Meter >> Configure
.
3. Select
Meter Function
, and choose one of the options listed in step 5 of
To
configure the inline meter for RS485 communication using SetApp: on page 28. If
the "Production" function was selected, enter the
Serial Number
of the inverter to
be metered.
4. Select
AC-Grid Connection (Top / Bottom)
, and specify whether AC inputs are
connected to the upper terminal blocks or the bottom terminal blocks.
5. To complete the configuration, select
Set and View Status
to view inline meter
status details.
Notes:
During the SetApp Device Manager's operation, the inline meter's blue LED will blink
rapidly, signaling that the meter is being configured.
If the AC grid is connected to the upper terminal blocks, the meter accuracy is 1%
(Class B). If the AC grid is connected to the lower terminal blocks, the meter
accuracy is 2% (Class A).
Once powered on, the inline meter will search for an Energy Net network to join, for
up to 48 hours. After 48 hours, the meter will stop searching for a network. Push the
Up and Down buttons simultaneously for 5 seconds in order to initiate another
search session.
Push the Up and Down buttons simultaneously for 5 seconds in the following cases:
When a new communications board is installed in the inverter
When connecting to a new inverter
When switching from RS485 configuration to Energy Net
To switch connectivity from RS485 to Energy Net, use SetApp to remove the RS485
meter from the connected device list. Push the Up and Down buttons
simultaneously for 5 seconds in order to initiate Energy Net search session. Use the
SetApp Device Manager to connect the meter to the inverter (see
Chapter 3: Configuration
29
Inline Energy Meter with SolarEdge Energy Net Communications
Summary of Contents for Inline Energy Meter
Page 46: ......