Chapter 7 – Prestart Inspection
TB42/TB50 – 0075251EE
33
Figure 7.18 – Guardrail System
Inspect all components of the guardrail system. The rails
and toeboards must all be in place and free of any dam-
age or deformation. Visually check the rail and toeboard
welds for cracks. All bolts and nuts fastening the plat-
form in place must be present and not show any signs of
looseness.
Inspect the gravity gate to be sure it is present, is not
damaged, and moves freely.
Inspect the optional swinging gate to see that it swings
freely, closes firmly, and is not deformed in any way. Make
sure the spring closes and secures the gate when the
gate is closed.
Lanyard Anchors
There are two lanyard anchors below the upper control
panel (refer to Figure 7.18).
Visually inspect the lanyard anchors to make sure they
are in place, are not deformed and are securely fastened
to the platform.
Operating Controls
Use the following procedure to operate the machine from
the upper controls.
1. Turn the battery disconnect switch on.
2. At the lower controls, pull the emergency stop but-
ton outward. Insert the key in the control selector
and turn the switch to the upper control position.
3. At the upper controls (refer to Figure 7.19), pull the
emergency stop button outward.
Figure 7.16 – Base End of Main Boom
Fasteners
Visually inspect all fasteners to see that none are miss-
ing or loose.
Pay particular attention to all of the bolts, nuts, rollpins,
collars, and snap rings that connect the booms and cyl-
inders. They should all be present, tight, and not dam-
aged in any way.
Raise the main boom to access the rotation bearing bolts
in the turntable (refer to Figure 7.17).
Inspect the rotation bearing bolts to ensure that none are
missing, damaged, or loose.
Figure 7.17 – Inside Turntable
Upper Control Station
Inspect the platform and upper controls only if all func-
tions operated properly from the lower controls.
Guardrail System
The guardrail system (refer to Figure 7.18) includes the
top rail, mid rail, toeboards and a gravity gate or optional
swinging gate.
Rotation Bearing Bolts
Mid Rail
Lanyard
Anchors
Gravity
Gate
Top Rail
Platform Foot
Switch
Toeboard
Summary of Contents for TB42
Page 14: ...Chapter 2 Specifications 10 TB42 TB50 0075251EE ...
Page 30: ...Chapter 6 Controls 26 TB42 TB50 0075251EE ...
Page 44: ...Chapter 7 Prestart Inspection 40 TB42 TB50 0075251EE ...
Page 58: ...Chapter 10 Emergency Operation 54 TB42 TB50 0075251EE ...
Page 66: ...Appendix A Glossary TB42 TB50 0075251EE ...
Page 68: ......