ROOF  ASSEMBLY 

SELECT: 

 

4 x 2.200 m Roof Sheets 

2 x 2.050 m Spouting 

4 x 1.100 m Barges 

1 x 2.050 m  Ridge Flashing 

1 x 2.020 m Ridge Beam 

2 x 0.200 m Jack Studs 

8 x 75mm Screws 

31 x 40mm Weatherseal Nails 

58 x Rivets 

 

IMPORTANT—FOR SHEDS WITH OPTIONAL CLEAR 

ROOF PANEL 

 

Assemble as below, making sure that the Clear Roof Sheets 
overlap the standard roof sheets on both sides.  
The Clear Roof Panel must be secured to the Top Plate and the 
Ridge Beam. Pre drill and fasten with the 40mm weatherseal 
nails provided.

.

 

STEP 1: 

 

 

Place the Ridge Beam on a level surface and use 2 x 75mm 
screws to secure the Jack Studs to the underside of the Ridge 
Beam, one at each end (

fig. 1

). 

 

 

Turn the Ridge Beam /Jack Stud assembly over and place it on 
the timber Top Plate in a central position.  

 

 

Secure with 2 x  75mm screws through the top of the Jack Studs 
into the Timber Top Plate (

fig. 2

). 

STEP 2: 

 

 

Position the first roof sheet with the centre slots over the 
middle of the Ridge Beam. Gently fold the roof sheet over 
the Ridge Beam so that the ends touch the front & back Top 
Plates.  

 

 

Repeat with second roof sheet. Ensure that slots in ends of 
sheets line up with each other.  

 

 

Rivet sheets together at overlaps ,one  rivet either side of the 
ridge beam (

fig. 3

).  

 

 

Repeat with remaining roof sheets 

11 

JACK STUD

 

TOP PLATE

 

RIDGE BEAM

 

fig. 1

 

fig. 2

 

SIDE 

WALL 

FRONT 

WALL 

BACK 

WALL 

SIDE 

WALL 

TOP 

BOTTOM 

RIDGE 

fig. 3

 

Summary of Contents for SS2020

Page 1: ...ASSEMBLY INSTRUCTIONS SS2020 BASE SIZE 2 020m x 2 020m...

Page 2: ......

Page 3: ...r cladding used in Smart Store Sheds Wash all surfaces annually using a hose and soft nylon brush Within 2 km of coast wash every 3 months as above After a storm wash the cladding and the gutters as s...

Page 4: ...255 m 2 Roof 2 200 m 4 Ridge Flashing 2 050 m 1 Door 3 4 Sheet 1 810 m 2 Barge 1 100 m 4 TIMBER Padbolt Support 0 140 m 1 Bottom Plates H4 Green Front Back 2 020 m 2 Spouting 2 050 m 2 Bottom Plates...

Page 5: ...e Back Wall Sheets Front Wall Sheet Door Jambs Front Wall Sheet Door Side Flashing Hinge Door Brace Door Top Bottom Channel Ridge Beam Jack Stud Ridge Flashing 5 ASSEMBLE FRONT PANEL 6 ASSEMBLE WALLS...

Page 6: ...coming through from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bot...

Page 7: ...Rivet sheets together STEP 2 Position door side flash ings and assemble door as shown Drill and rivet as per dia gram ensuring rivets penetrate into door sheet STEP 4 Rivet door brace flashings onto b...

Page 8: ...s to the Top Plate at each end making sure that the top corners of the sheets are flush with the top of the Top Plate and that the sides of the wall sheet overhang the Top Plate by approx 15mm as show...

Page 9: ...e using two clouts per pan STEP 4 Nail the wall sheets to the Bottom Plate at each end ensuring that each side of the wall sheets overhangs the Bottom Plate by 15mm and that the distance between the T...

Page 10: ...the Door Jamb Flashing Ensure the door closes properly then fit remaining rivets STEP 3 Place 2 x Wall Sheets on timber Ensure that the top of the sheets are flush with the top of the Top Plate and t...

Page 11: ...2 per join screw the Top and Bottom Plates together in the corners STEP 2 Repeat Step 1 with the second Side Panel ensuring that the Side Panel overlaps the Back Wall Panel STEP 3 Stand up the Front...

Page 12: ...secure the Jack Studs to the underside of the Ridge Beam one at each end fig 1 Turn the Ridge Beam Jack Stud assembly over and place it on the timber Top Plate in a central position Secure with 2 x 75...

Page 13: ...eet then using 1 x 40mm Weatherseal nail fix Roof Sheet through the pan into the Top Plate Repeat at the front ROOF ASSEMBLY CONT 12 STEP 4 Centralise the Roof at the right hand end with the Ridge Bea...

Page 14: ...e Bottom Plate and the concrete slab A 10mm masonry drill bit is required OPTIONAL SENTRY FLOOR Position the Floor Joists centrally between the side Base Plates and skew nail each end with two 75mm na...

Page 15: ......

Page 16: ...s less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Fast...

Reviews: