background image

 

 

CONGRATULATIONS ON PURCHASING A DURATUF SMART STORE SHED. 

 

BEFORE YOU BEGIN THE ASSEMBLY PLEASE NOTE SOME IMPORTANT POINTS:

 

2

 

 

 

 

BEFORE YOU START:

 

 

• 

Read all instructions carefully

 

• 

Identify all parts and check quantities against parts list

 

• 

Select a level site

 

• 

Do not mark cladding with pencil as lead can cause corrosion to cladding

 

• 

During assembly, ensure all drill filings are removed between  layers of steel, before riveting together

 

 

 

SAFETY:

 

 

• 

Do not attempt to build your shed in high winds

 

• 

Beware of sharp edges, we recommend that you use gloves

 

• 

Protect your eyes and ears

 

• 

For ease of assembly, use a friend to help 

 

 

 

TOOLS REQUIRED:

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

WARRANTY REQUIREMENTS

:

 

 

 

The following maintenance process needs to be adhered to, to qualify for the steel warranty of your Duratuf Smart store 

shed.

 

 

• 

Wash all surfaces annually using a hose and soft nylon brush.

 

• 

Within 2 km of coast –

 

wash every 3 months as above. After a storm, wash the cladding and the gutters as soon 

as possible to remove any highly corrosive salt deposits.

 

• 

Volcanic Ash Fallout –

 

wash as soon as possible, removing fall out from roof and gutters.

 

• 

Do not allow manures, chemicals or other corrosive materials to have direct contact with cladding

.

 

DRILL

 

RIVETER

 

3.5mm DRILL BIT

 

HAMMER

 

LADDER

 

TAPE MEASURE

 

HEX DRIVE

 

NAIL PUNCH

 

SQUARE DRILL BIT

 

SKILL SAW 

 

(timber floor only)

 

Summary of Contents for SM2520

Page 1: ...ASSEMBLY INSTRUCTIONS SM2520 BASE SIZE 2 520m x 2 020m...

Page 2: ......

Page 3: ...eyes and ears For ease of assembly use a friend to help TOOLS REQUIRED WARRANTY REQUIREMENTS The following maintenance process needs to be adhered to to qualify for the steel warranty of your Duratuf...

Page 4: ...2 200m 5 Door Sheet Narrow 1 850m 2 Door Sides 1 850m 2 Door Jamb 1 890m 2 Door Brace 1 160m 2 Barge 1 102m 4 Ridge Cap 1 550m 2 Door Top Bottom 0 945m 2 Jack Studs 45 x 30 0 200m 2 Hardware Pack 1 To...

Page 5: ...TY DIAGRAM Front Back Bottom Plates H4 Green 2 520 m 2 Front Back Top Plate H1 Red 2 520 m 2 Side Wall Bottom Plates H4 Green 2 020 m 2 Side Wall Top Plates H1 Red 2 020 m 2 Ridge Beam 90 x 45 2 520m...

Page 6: ...AY FOUNDATION 2 ASSEMBLE DOOR QUICK OVERVIEW Door Sheets Padbolt Support Top Plate Back Side Wall Sheets Barge Flashing Spouting Roof Sheets Top Plate Side Top Plate Front Bottom Plate Side Back Wall...

Page 7: ...ng through from underneath During construction you may raise the bottom timber plate to allow the wall cladding to protrude 20mm below the bottom plate This will stop water flowing between the bottom...

Page 8: ...bottom flashings and assemble door as shown Drill and rivet as per diagram STEP 4 On the back of the door place door braces in posi tion as shown in fig 3 Ensure that the top and bottom ends of the b...

Page 9: ...overhang the Top Plate by approx 15mm as shown Check that the Top Plate is straight then nail the Wall sheet to the Top Plate 2 clouts per pan see fig 1 Standard Shed Bottom Plate will protrude be low...

Page 10: ...sing two clouts per pan STEP 4 Nail the wall sheets to the Bottom Plate at each end ensuring that each side of the wall sheets overhangs the Bottom Plate by 15mm and that the distance between the Top...

Page 11: ...ts on timber Ensure that the top of the sheets are flush with the top of the Top Plate and that the sides of the wall sheets overhang the Top Plate by 15mm as shown Nail wall sheets to Top Plate two c...

Page 12: ...2 per join screw the Top and Bottom Plates together in the corners STEP 2 Repeat Step 1 with the second Side Panel ensuring that the Side Panel overlaps the Back Wall Panel STEP 3 Stand up the Front...

Page 13: ...nd use 2 x 75mm screws to secure the Jack Studs to the underside of the Ridge Beam one at each end fig 1 Turn the Ridge Beam Jack Stud assembly over and place it on the timber Top Plate in a central p...

Page 14: ...Rivet the Ridge Cap to the centre of the roof using 8 x rivets as shown fig 2 Clout Screw fig 1 Pan Rib fig 2 IMPORTANT Use 50mm Clouts only on ribs covered by flashings shown in fig 2 Predrill holes...

Page 15: ...LOOR KIT OPTIONAL Position the Floor Joists centrally between the side Base Plates and skew nail each end with two 75mm nails Check that the shed is sitting level and square Check that the diagonal Bo...

Page 16: ...s less than 200g m2 as published by Branz Warranty certificate being returned to manufacturer within 21 days of purchase together with proof of purchase This warranty does not cover the following Fast...

Reviews: