(9) Before operating the operator shall conduct a comprehensive safety inspection,

confirm the safety guards and safety devices of the machine before starting the

machine to normal after all.

(10) After machine maintenance, to ensure the safety devices and protective cover,

complete and accurate installation in the original location.

(11) Only off the power, gas supply, all the moving parts of the machine is completely

stopped and disconnect the power before they can repair, maintenance,

replacement and cleaning machine debugging.

(12) Replacement parts must use original parts, otherwise it will cause danger or

damage to the machine.

(13) In the case of the machine must be running unattended operator when the operator

leaves the machine, you must turn off the power.

(14) Always check all power lines and ground lines, ensure that the machine's

electrical system has good insulation and grounded. Not use defective wires.

(15) Prohibiting the use in wet or explosive environment, or they may cause serious

danger.

(16) Keeping the work environment clean, provide adequate lighting.

(17) Prohibit children and visitors close to the machine, the operator at least 18

years of age have the ability to predict the presence of dangerous machines.

(18) Do not drink after fatigue and have a hypnotic effect and taking similar drugs

operate the machine.

(19) The operator must not wear loose clothing, not wearing a tie, gloves or jewelry

(such as rings, bracelets, watches, etc.).

(20) Long hair must be wrapped with a wig and reliable, to prevent hair caught in

the machine inside.

(21) When operating the machine is recommended to wear the necessary personal

protective equipment, such as wearing ear protection to reduce the risk of

hearing loss.

1.2 Equipment usage rules

(1) At the discharge end of the machine should ensure that sufficient space-space

ratio should be at least the length of the longest length of the workpiece large

500mm.

(2) User-equipped blade, cutter and cutter machine sizes must comply with the

requirements of the original configuration, the user must be selected in line

Summary of Contents for SNB-K3A

Page 1: ...SNB K3A AUTOMATIC EDGE BANDER MANUAL SNB K3A AUTOMATIC EDGE BANDER 1...

Page 2: ...aintenance 8 Chapter 3 Mechanical uses and features 10 Chapter 4 Mechanical structure 10 Chapter 5 The main technical parameters 11 Chapter 6 Transport 12 Chapter 7 Equipment Installation 12 Chapter 8...

Page 3: ...2 Packing List 1 Automatic edge banding machine 1 2 Instructions 1 3 Tools Allen wrench 1 Cross screwdriver 1 Flathead screwdriver 1...

Page 4: ...on and maintenance operation and maintenance personnel must observe the following Before the operation or maintenance be sure to read and understand this manual To read this manual safety notice and a...

Page 5: ...3 Assembly maintenance and repair personnel must fully understand the operating instructions and in strict accordance with the requirements of the job 4 After the machine stops adjust or remove the pr...

Page 6: ...the use in wet or explosive environment or they may cause serious danger 16 Keeping the work environment clean provide adequate lighting 17 Prohibit children and visitors close to the machine the ope...

Page 7: ...e components If abnormal should be repaired by qualified service personnel replacement parts should be used original parts 8 Keep knives sharp should be replaced blunt deformed defective blade cutter...

Page 8: ...ve humidity 90 No condensation Power frequency Altitude 1000m Ambient temperature 0 C 40 C Silo temperature 0 C 40 C 1 4 Noise statement Noise measurements were performed according to standard IS07960...

Page 9: ...off the main power switch and disconnect the power strictly prevent accidental machine startup When the machine work you must use the vacuum suction device Regular cleaning can prolong its life and i...

Page 10: ...int refueling Rust oil 3 Molybdenum disulfide lithium grease 2 Every 80 working hours Glue pot High temperature grease injection pressure of linear bearing with grease gun 3 Molybdenum disulfide lithi...

Page 11: ...ge bonding and dressing the processing after the sheet edge is evenly and firmly trimming smooth and more durable and beautiful Characteristics The machine can from the plate into the auto completion...

Page 12: ...tomatic edge banding machine sheet thickness 10 50mm edge thickness 0 4 3mm minimum working plate width 50mm minimum working length 140mm higher than the maximum size of sheet sapwood per side 2mm fee...

Page 13: ...reenhouse and dry environment and the cover is sealed by a plastic bag Chapter 7 Machine installation 7 1 Machine installation 1 the installation of the machine should be far away from the vibration s...

Page 14: ...se refer to the junction box office Voltage fluctuation range 10 frequency fluctuation range 0 5Hz 3 The machine with 5 copper core wires copper wires for power lines into the 4 The cross sectional ar...

Page 15: ...ne tool has passed the precise adjustment and the strict test before leaving the factory has not been related to the training or has not specially specially specially specially to instruct not to be a...

Page 16: ...achine touches the travel switch push conveyor cylinder edge forward Board to enter the end of the trip to leave the trip stop feeding Figure 5 8 4 Edge system This system adopts the edge banding mach...

Page 17: ...g rod 1 edge band limiting plate 3 send belt wheel 5 edge band height positioning column 7 has been to the cutter 14 edge position c According to the edge with the height and the adjustment of edge wi...

Page 18: ...tretch adjustment edgeband plate is higher than that of unilateral height adjustment Note the above two data ready standard adjustment at the factory in the normal working state of the equipment witho...

Page 19: ...to operating temperature should be extended 10 minutes to be coated rollers to operating temperature before startup otherwise it might damage cots d Users must according to the requirement of edge mat...

Page 20: ...n motor 0 55KW 2 200Hz 18000RPM and profiling track structure ensures that the motor cutting cut section of smooth and tidy Before and after the butting motor adopts imported cylinder imported linear...

Page 21: ...wer circular arc regulating handles 2 and 5 are small so that the amount of the trimming of the circular arc is appropriate After adjustment lock the handle Note in the regulation because the regulati...

Page 22: ...hickness greater than the thickness of the band edge of the current device used you need to first scraping amount regulating handle 1 and 4 increase so that the upper and lower scraping the right amou...

Page 23: ...the handle Figure 12 8 8 Buffing system The edge machine buffing system is to clean up the plate processing and play a good role in polishing Polishing assembly consists of a two motor with cotton pol...

Page 24: ...e plate FIG 15 Figure 15 Figure 16 8 9 Preheat In the low temperature environment influence of edge effect the preheating switch can be turned on the left side of the fuselage for preheating plate Fig...

Page 25: ...e trimming system common abnormal phenomenon and its elimination phenomenon reason solution The trim on the wood is not sustainable The wood plane can not accurately track profile Increase the pressur...

Reviews: