28
BUOYANCY TUBE- Commissioning
II
-1- Commissioning
Be sure to observe the correct procedural sequence at all times. Proceed step by step, referring each
time to the pages indicated for explanation of procedures.
PROCEDURE
1. Inventory: become familiar with boat
components
2. Activate valves in inflating position
3.Inflate boat to the correct operation
pressure
PAGE
26-27
30-31
31
32-33
SECTION
Inventory / description of the
deck layout
Inflating system
Inflating the boat
Pressure