Check the Serverboard Setup
After you install the server in the rack, you will need to open the unit to make sure the serverboard
is properly installed and all the connections have been made. Before operating the server for the
first time, it is important to remove any protective film covering the top of the chassis. The
removal of this film allows for proper ventilation and cooling.
Removing the Chassis Cover
Use the following procedure for removing the chassis cover as illustrated in
Note:
Ensure that the system is not turned on or connected to AC power.
1. If the server is rack-mounted, grasp the two front handles and pull the server straight out
until it locks.
You will hear a click when it locks. To remove the system from the rack completely, depress
the locking tabs on the chassis rails (push the right-side tab down and the left-side tab up) to
continue to pull the system out past the locked position.
2. If the two optional screws are securing the cover to the chassis, remove them, one from each
side of the cover.
3. Press both release tabs at the same time to unlock the cover and slide the cover to the rear.
4. Lift the cover from the chassis.
Summary of Contents for SGI UV 30
Page 1: ...SGI UV 30 System User Guide 007 6419 003 ...
Page 4: ......
Page 8: ......
Page 10: ......
Page 12: ......
Page 35: ...Install the System into a Rack 007 6419 003 19 Figure 3 2 Installing the Inner Rails ...
Page 39: ...Check the Serverboard Setup 007 6419 003 23 Figure 3 4 Accessing the Inside of the Chassis ...
Page 51: ...Replacing a Power Supply 007 6419 003 35 Figure 5 3 Replacing a Power Supply ...
Page 53: ...Replacing Disk Drives 007 6419 003 37 Figure 5 4 Removing HDD Carrier from Chassis ...
Page 54: ...38 007 6419 003 5 Chassis Maintenance Figure 5 5 Removing Dummy Drive from Carrier ...
Page 57: ...Replacing System Fans 007 6419 003 41 Figure 5 7 System Fans ...
Page 58: ......
Page 66: ......
Page 68: ......