Instruction Manual AquaMaster
Commissioning
40
12745E/4
5
Commissioning
The initial start-up of the web user interface via the Ethernet interface is described in the
Reference Manual. If malfunctions occur, consult the Section 9.
Proceed with the initial start-up in accordance with the following table:
WORKSTEP
ADDITIONAL INFO / IMAGES
1.
Check photometer mounting and the associ-
ated peripherals.
1.1: Ensure the inlet and outlet are correctly
mounted on the photometer.
Section 4
1.2: Ensure the sensors are correctly mounted in
the measuring cell block.
Section 4.8
2.
Check the piping of the complete system.
Check the water connections, inlet and outlet
connections, and tubing.
3.
Establish sample feeding to the photometer
as follows:
3.1: Fasten optics unit to docking station.
3.2: Ensure the flow regulator valve (A) to the in-
strument is closed.
3.3: Ensure the inlet regulator valve (B) to the
measuring cell block is closed.
3.4: Establish main water supply to the system.
3.5: Open flow regulator valve (A) to the instru-
ment.
3.6: Adjust water jet according to Section 8.2.2
and close the measuring cell of the photometer.
3.7: Check the sight glass (C) to ensure that there
is continuous water flow through the photometer.
3.8: Mount and fasten the optics unit again on
measuring cell of the photometer.