Installing
4.2 Procedure for mounting the device
SIWAREX WL200
18
Operating Instructions, 07/2016, A5E02199611B-03
NOTICE
Damage to load cells through incorrect mounting
•
Provide indented claws or crane eyebolts on the load bearer to ensure that hoisting gear
can be used safely.
•
Load cells must never be overloaded. Put the load carrier down slowly for this reason.
With load cells of smaller rated loads in particular, there is a risk of stretching the load
cell bodies when attaching force transfer devices, e.g. when tightening locknuts.
•
Adjust the existing overload protection to ensure that it can still reliably sense transfer of
the required load. The overload protection must permit a rise in weight unhindered until
the setpoint weight is reached.
•
Protect the gap between the load cell and overload protection from the build up of dirt or
ice.
•
The load must be introduced in the measuring direction of the load cell. Torsional and
bending moments, eccentric loads and lateral forces are disturbances. These
disturbances falsify the measured result and can damage the load cell if the permissible
limits of the load cell and mounting components are exceeded.
The mounting components normally allow so much room for movement that heat
expansion will not result in lateral loading.
NOTICE
Destruction of load cells
Proceed carefully with installation. The load cells can be destroyed if they are installed
incorrectly.
4.2
Procedure for mounting the device
Procedure for mounting the device
1.
Observe the installation guidelines for the mounting components.
–
You can find dimension drawings of installation elements under Dimension drawings
(Page 69).
–
Lay the cables for the load cells through cable glands in the form of a vertical
downwards loop to discourage the penetration of water.
2.
Check that the load cells and mounting components are installed correctly, e.g. by
checking the mounting dimensions and oscillation distances.
See also
Nameplate layout (Page 15)
Summary of Contents for SIWAREX WL200 Series
Page 6: ...Table of contents SIWAREX WL200 6 Operating Instructions 07 2016 A5E02199611B 03 ...
Page 20: ...Installing 4 3 Dismantling SIWAREX WL200 20 Operating Instructions 07 2016 A5E02199611B 03 ...
Page 102: ...Index SIWAREX WL200 102 Operating Instructions 07 2016 A5E02199611B 03 W Wheatstone bridge 14 ...