5.2.6
Setting down the machine
Requirements
The following preconditions must be satisfied before setting down the machine at the
installation location:
● The mating faces must be clean.
● The anti-corrosion protection paint has been removed from the mating faces, such as the
machine mounting feet, flange, ...
Setting down the machine
Set down the machine slowly and carefully at the installation location to avoid any impact.
5.2.7
Roughly aligning the machine
Requirement
The transmission element such as a coupling half has already been pulled on.
Roughly aligning the machine
● For horizontal positioning, push the motor sideways across the foundation. When doing so,
ensure that the axial position is maintained.
5.3
Installing the machine
5.3.1
Preconditions for smooth, vibration-free operation
Preconditions for smooth, vibration-free operation:
● Stable foundation design as per DIN 4024
● Precise alignment of the machine
● Correct balancing of parts to be fitted to the shaft end.
● Maintaining the vibration velocity according to ISO 10816-3
Assembling
5.3 Installing the machine
LOHER CHEMSTAR 1PS5
Operating Instructions 03/2014
49
Summary of Contents for SIMATIC S5 1P 243
Page 2: ...11 03 2014 02 49 V4 00 ...
Page 12: ...Introduction LOHER CHEMSTAR 1PS5 12 Operating Instructions 03 2014 ...
Page 20: ...Safety notes 2 11 Ventilation LOHER CHEMSTAR 1PS5 20 Operating Instructions 03 2014 ...
Page 66: ...Electrical connection 6 2 Connecting LOHER CHEMSTAR 1PS5 66 Operating Instructions 03 2014 ...
Page 124: ...Disposal 11 4 Disposal of components LOHER CHEMSTAR 1PS5 124 Operating Instructions 03 2014 ...
Page 136: ...Quality documents C 4 Data LOHER CHEMSTAR 1PS5 136 Operating Instructions 03 2014 ...
Page 140: ...Index LOHER CHEMSTAR 1PS5 140 Operating Instructions 03 2014 ...
Page 141: ...AC EC Declaration of Conformity U161 AB EC Declaration of Conformity U163 AA R No 20000h U165 ...