Commissioning
6.2 Commissioning guidelines
SIMATIC ET 200pro FC-2 converter
74
Operating Instructions, 04/2018, FW V4.7 SP10, A5E34257324B AF
6.2
Commissioning guidelines
Procedure
1.
Define the requirements to
be met by the drive for your
application.
(Page 74)
2.
Restore the factory settings
of the inverter if necessary.
(Page 77)
3.
Check whether the factory
setting of the inverter is
appropriate for your
application.
If not, start basic
commissioning.
(Page 79)
4.
If necessary, set further
functions in the inverter.
(Page 91)
5.
Save your settings.
(Page 193)
You have commissioned the inverter.
❒
6.3
Preparing for commissioning
Overview
Before starting commissioning, you must know the answer to the following questions: