System commissioning
5.1 Acceptance of the system
Fail-safe operation of the Mobile Panel 277F IWLAN
78
Function Manual, 08/2008, 6AV6691-1FQ01-2AB0
Acceptance of the safety program
● Print and archive the safety program.
● Check the printed copy of the safety program for existence of the criteria specified in the
"S7 Distributed Safety, Configuring and Programming" manual, chapter "Acceptance of a
safety program."
● Download the entire safety program to the F-CPU.
● Test all functions of the safety program.
A detailed description is provided in the "S7 Distributed Safety, Configuring and
Programming" manual, chapter "Acceptance of the configuration for the F-CPU and fail-safe
I/O."
Acceptance of the effective ranges and transponders
● For acceptance of the effective ranges and transponders you must determine a CRC
checksum in the plant and enter it in the project. After subsequent project transfer to the
HMI device you can operate the plant with the HMI device.
● Generate a printed copy of the project with output format "Complete."
● Archive the project.
A detailed description about the printing and archiving of projects is provided in the WinCC
Online Help.
Note
If you change transponders in the plant you must execute another acceptance of the plant.
See also
Accepting effective ranges and transponders (Page 79)