Chapter 2
Installing the Device
RUGGEDCOM M969F
Installation Guide
10
Unpacking the Device
1. Review the relevant certification information for any regulatory requirements. For more information, refer to
2. Mount the device.
3. Connect the failsafe alarm relay.
4. Connect power to the device and ground the device to safety Earth.
5. Connect the device to the network.
6. Configure the device.
Section 2.2
Unpacking the Device
When unpacking the device, do the following:
1. Inspect the package for damage before opening it.
2. Visually inspect each item in the package for any physical damage.
3. Verify all items are included.
IMPORTANT!
If any item is missing or damaged, contact Siemens for assistance.
Section 2.3
Mounting the Device
The RUGGEDCOM M969F is designed to be mounted on a panel by affixing the top and bottom flanges of the
device to a panel using screws.
IMPORTANT!
Heat generated by the device is channeled outwards from the enclosure. As such, it is recommended
that 2.5 cm (1 in) of space be maintained on all open sides of the device to allow for some
convectional airflow.
Forced airflow is not required. However, any increase in airflow will result in a reduction of ambient
temperature and improve the long-term reliability of all equipment mounted in the rack space.
NOTE
For detailed dimensions of the device with panel mount hardware installed, refer to
.
To mount the device to a panel, do the following:
1. Place the device against the panel and align the flanges with the mounting holes.
Summary of Contents for RUGGEDCOM M969F
Page 4: ...RUGGEDCOM M969F Installation Guide iv ...
Page 10: ...Preface RUGGEDCOM M969F Installation Guide x Customer Support ...
Page 18: ...Chapter 1 Introduction RUGGEDCOM M969F Installation Guide 8 Decommissioning and Disposal ...
Page 38: ...Chapter 5 Technical Specifications RUGGEDCOM M969F Installation Guide 28 Dimension Drawings ...
Page 48: ...Chapter 6 Accessories RUGGEDCOM M969F Installation Guide 38 LC Fiber Optic 2 unit ...