Mammomat 1000/3000
Register 03
SP B7-230.033.07
Page 2 of 8
Siemens-Elema AB
Installation and Start-Up
Rev. 03
11.99
SPS-UD
Solna, Sweden
3 - 2
Preparatory work
Unpacking the stand
3
Unpacking
1.
Open the stand crate by removing the top (1) and then the side wall (2).
2.
Take out all enclosed packages (accessories, installation material, cover panels
etc.) from the crate.
3.
Remove the wooden supports.
4.
Remove the remaining walls (3).
5.
Move the stand and pallet to the site of erection.
6.
Upend the stand (4), with pallet (5) (two persons are required).
7.
Loosen the four bolts (6) and remove the pallet (5).
Fig. 1
Unpacking the stand
MAM00167
1
2
2
1
3
6
5
4