14
Installation and Service Manual
7.
Chiller Installations:
Route insulated beverage line
from the coil outlet (
5C
) up through either the back or
bottom of tower (
4A
) as shown (
See Figures 4 and
5
). Route insulated beverage line through left side
hole in the valve mount plate (
4B
) as shown (
See
Figure 4
). Connect insulated beverage line to left
side of barb fitting (
4C
) and secure line to barbed
fitting with otiker clamp (
See Figure 4
). Connect the
last insulated beverage line to right side of barbed
fitting (
4E
) and secure line to barbed fitting with otiker
clamp (
See Figure 4
). Wrap fitting and insulated bev-
erage lines (
4D
) with cork tape insulation (
See Fig-
ure 4
).
Installation of cork tape must be done prop-
erly to prevent condensation and temperature
gain of
circulating water
.
Cooling Coil and Chiller Common Instructions
8.
Route insulated beverage line through right side hole
in the valve mount plate (
4F
) as shown (
See Figure
4
). Route insulated beverage line either through back
or bottom of tower (
See Figure 4
).
9.
Connect insulated beverage line from right side of
tower to pump inlet barbed fitting (
1C
) and secure
with otiker clamp (
See Figure 1
). Connect potable
water supply line (3/8 ID line size) to barbed pump
connection (
1D
) and secure line with otiker clamp (
See
Figure 1
). After all line connections have been made
ensure potable water supply is flowing or turned on
and check for leaks. If no leaks are present dispense
water through the tower to purge any trapped air from
the recirculation loop and pump. Connect power sup-
ply cord (
1E
) from recirculation pump (
1A
) to recep-
tacle (
1F
) on the power supply (
1G
) or to a separate
power outlet or receptacle (
See Figure 1
).
INSTALLATION
RECIRCULATION LINES AND PUMP
FIGURE 4
4A
4B
4C
4F
4E
4D
5B
5C
5A
FIGURE 5