INSTALLATION
MANUAL
Product:
Document #:
Rev:
Page:
SEAKEEPER 26 / 20HD
90265
7
1 of 21
Section 1: MECHANICAL INSTALLATION
1.0
Introduction
This document is intended to give details and guidance to a boat builder or equipment installer to
install the Seakeeper 26. The Seakeeper can produce loads up to 35.89 KN (8,070 lbs.) at each
of the four mounts and careful consideration should be given to foundation design to ensure it can
transfer these loads into the hull. These loads do NOT include vessel motion accelerations, such
as vertical slam loads which can be significant for high speed performance vessels.
There are two methods of installing the Seakeeper 26:
1) Bolt-In Installation
2) Bond-In (Saddle) Installation
It is assumed that the installer is familiar with bonding using high strength adhesives or
mechanical fasteners to marine structures and has performed structural analysis to assure
the structure to which the Seakeeper mounts can properly transfer the loads the Seakeeper
creates into the hull structure. If the installer has any doubt about the ability of the
structure to transfer the loads to the hull, then he should contact a licensed naval architect
or marine engineer to do a structural analysis.
The installer should review the following list of reference drawings to ensure the installation
procedure is fully understood.
Reference Drawings
•
90244 Seakeeper 26 Hardware Scope of Supply
•
90416 Seakeeper 20HD Hardware Scope of Supply
•
90271 Seakeeper 26/20HD Installation Details
– Bolt in Method
•
90272 Seakeeper 26/20HD Installation Details
– Bond in Method
•
90085 Seakeeper 26/20HD Bond-in Saddle Kit
•
90086 Seakeeper 26/20HD Bolt-In Installation Kit, M16, Through-Bolt
•
90614 Seakeeper 26/20HD Bolt-In Installation Kit, M16, Blind-Hole
•
90088 Seakeeper 26/20HD Bond-In Installation Fixture Kit
•
90089 Seakeeper 26/20HD Bolt-In Installation Fixture Kit
•
90310 Seakeeper 26/20HD Cable Block Diagram
•
90320 Seakeeper 26/20HD Cooling Water Schematic
FIGURE 1
– SEAKEEPER 26