TO INSTALL: Plumbing
The water supply and drain should be roughed in
and ready at the point of installation. A wall outlet
directly behind the ice machine will make
undercounter installation easier. All electrical,
water and drain connections must conform to local
codes.
Installation Cautions:
Although the DCE33 has
been designed to be serviced in place, in some
cases it may be necessary to pull the unit out for
service. For that reason do not restrict access to
the cabinet at the front - top and bottom.
If a floor is to be installed after the ice machine,
shims the thickness of the floor should be installed
under the DCE33 to keep the machine level with
the floor. Also, allow 1/8" clearance on each side of
the cabinet.
Installations on a slab:
Use a pump
(DCE33PA-1) model and pump the water to the
point of drainage. Pump models will pump 1 story
high.
Installations over a crawl space or basement:
Either gravity drain or pump model units may be
used, if there is not enough room behind the
machine for a drain/waste receptacle, the drain will
have to be below the floor.
ALL PLUMBING MUST MEET LOCAL CODES
Note: When installed in a corner, the door
swing may be limited due to handle contact
with the wall or cabinet face.
DCE33
September 2011
Page 5
Normal Drain Line, Pitched
Down From Ice Machine
With Trap, Causes Poor Draining
With Trap And Vent,
Draining Is Normal
EXAMPLES OF GRAVITY DRAIN TUBE INSTALLATIONS
From Ice Machine
To Drain
Good Draining
Poor Draining
Good Draining
Shims
Install Unit
Flush With Floor