Testing, Troubleshooting, and Maintenance
Testing Philosophy
Commissioning Testing
SEL performs a complete functional check and calibration of each SEL-400
series relay before shipment so that your relay operates correctly and accurately.
You should perform commissioning tests to verify proper connection of the relay
to the power system and all auxiliary equipment. Check control signal inputs and
outputs. Check breaker auxiliary inputs, SCADA control inputs, and monitoring
outputs. Use an ac connection test to verify that the relay current and voltage
inputs are the proper magnitude and phase rotation.
Brief fault tests confirm that the relay settings and protection scheme logic are
correct. You do not need to test every relay element, timer, and function in these
tests.
At commissioning, use the relay
METER
command to verify the ac current and
voltage magnitude and phase rotation (see
Examining Metering Quantities on
Use the
PUL
command to pulse relay control output operation. Use the
TAR
command to view relay targets and verify that control inputs are operational. Use
TEST DB
,
TEST DB2
, and
TEST FM
to check SCADA interfaces. (See
, and
for
information on these relay commands.)
lists guidelines for commissioning testing. For further discussion of
these tests, see
Checking Relay Operation
in
Section 3: Testing
of the product-
specific instruction manual.
Table 10.1
Acceptance Testing
Details
Description
Time
Test when qualifying a relay model for use on the utility system.
Goals
a) Confirm that the relay meets published critical performance specifications
such as operating speed and element accuracy.
b) Confirm that the relay meets the requirements of the intended application.
c) Gain familiarity with relay settings and capabilities.
Test
Test all protection elements and logic functions critical to your intended application.
Table 10.2
Commissioning Testing
Details
Description
Time
Test when installing a new protection system.
Goals
a) Validate all system ac and dc connections.
b) Confirm that the relay functions as intended using your settings.
c) Check that all auxiliary equipment operates as intended.
d) Check SCADA interface.
Tests
Test all connected/monitored inputs and outputs, and the polarity and phase rota-
tion of ac connections. Make simple checks of protection elements. Test commu-
nications interfaces.
Summary of Contents for SEL-421-4
Page 6: ...This page intentionally left blank ...
Page 14: ...This page intentionally left blank ...
Page 30: ...This page intentionally left blank ...
Page 104: ...This page intentionally left blank ...
Page 128: ...This page intentionally left blank ...
Page 536: ...This page intentionally left blank ...
Page 584: ...This page intentionally left blank ...
Page 616: ...This page intentionally left blank ...
Page 696: ...This page intentionally left blank ...
Page 750: ...This page intentionally left blank ...
Page 755: ...Instruction Manual PM400 01 NB SEL 400 Series Relays Instruction Manual 20171006 ...
Page 776: ...This page intentionally left blank ...
Page 932: ...This page intentionally left blank ...
Page 976: ...This page intentionally left blank ...
Page 1024: ...This page intentionally left blank ...
Page 1038: ...This page intentionally left blank ...
Page 1064: ...This page intentionally left blank ...
Page 1128: ...This page intentionally left blank ...
Page 1206: ...This page intentionally left blank ...
Page 1316: ...This page intentionally left blank ...
Page 1350: ...This page intentionally left blank ...
Page 1464: ...This page intentionally left blank ...
Page 1468: ...This page intentionally left blank ...
Page 1492: ...This page intentionally left blank ...
Page 1518: ...This page intentionally left blank ...