GP-MSJV-BX-07A
STV-JZ Manual
RD: MAR 2009
RL: 07A - BA
Page 11
19”
10”
10”
FIGURE 10 BOLTING BURNER TO FLANGED TUBE
1 Fifth Nut (Holding Inner Burner
to Housing)
2 Lock Washers (4) Four
3 Nuts (4) Four
4 Gasket
Align the four burner bolts
through flange on tube, secure
tightly with lock washers and
nuts
Do not loosen or remove fifth nut
(#1) directly below burner cup
Secure suspension chain to eye
hook in order to stabilize burner
HEATER SHOULD BE SPACED AWAY FORM A WALL OR OB-
STRUCTION THAT WOULD RESTRICT OR LIMIT ACCESS TO
THE SIDES OF THE BURNER PANEL FOR SERVICE OR RE-
PAIRS.
(SEE PRE-INSTALLATION SURVEY AND MOUNTING CLEAR-
ANCES)
e) The coupler is now in place on the ‘burner-end’ side of the hanger
8) CHECK THAT THE SECOND TUBE IS LEVEL, ALIGNED HORIZONTALLY AND
VERTICALLY WITH THE FIRST TUBE – MAKE ADJUSTMENT AT SUSPENSION
POINTS AS REQUIRED
9) Install the reflector over the second tube fastening to the hangers at each end
10) Repeat the previous steps assembling one section of tube and reflector at a time until the
system is complete
11) ENSURE THAT THE SYSTEM IS LEVEL AND THAT ALL TUBES ARE ALIGNED
HORIZONTALLY AND VERTICALLY – MAKE ADJUSTMENT AT SUSPENSION
POINTS AS REQUIRED
12) Mount the Burner to the first tube flange using the four nuts and bolts provided
a) TIGHTEN THE BOLTS IN AN OPPOSITE CORNER SEQUENCE AND ENSURE
THAT THE BURNER IS IN HORIZONTAL ALIGNMENT WITH THE TUBE
13) The ‘center of gravity’ of the burner is slightly off-center to the tubes. So, in order to pre-
vent side rotation of the burner:
Install a support chain from the eye hook on the burner to a point approximately 8 to 10
inches away (towards the burner) from the first tube hanger
i) DO NOT fasten the chain from the burner to the first hanger suspension point
ii) The chain will angle back over the burner and allow “straight back” movement of the
burner when the system heats up and expands