GB-15
Cover
(included with
base unit)
Riser Kit
GB-20
GB-25
Figure 4
Finished floor
Fasten Cover
Install Riser
Figure 1
Remove cover
Install ring / bolts
Finished floor
X"
Figure 2
Finished floor
Install
Riser
Measure
X"
Figure 3
Riser
Mark, cut,
and deburr
Measurement from
Figure 2
Riser
Bolts
Gasketed Ring
SR16 Riser Kit
(Sold Separately)
2-1/8" Min.
Figure 5
16" Max.
Tools included (with riser kit)
Silver permanent marker
•
Tools Needed:
Tape measure
•
Phillips head screwdriver
•
Jigsaw or
•
Cordless circular saw or
•
Reciprocating saw
•
Riser Assembly Instructions/Steps:
If unit is to be buried, you will need an SR16 riser kit (sold separately). The 16 Series TeleGlide Riser System for these
1.
models allows riser heights from 2-1/8" above standard unit up to 16". Only ONE riser may be used per base unit to allow
sufficient access to internal serviecable components. See Figure 5.
If more than 16" of riser height is needed, you will need to adjust jobsite requirements OR purchase the next available
2.
model with a 24 Series TeleGlide Riser System which allows taller riser heights.
Once unit is set so that pipe connections line up with jobsite piping, remove cover from unit. Fasten yellow gasketed ring to
3.
unit with hardware provided in separate riser kit. Ring flange with 4 bolt notches faces down against the unit. See Figure 1.
Push riser into ring until it stops (about 1 inch). See Figure 2.
4.
Measure the distance from the top edge of the riser down to the finished floor. Make sure to account for any future tile work
5.
in your measurment. See Figure 2.
Remove riser from ring. Take measurement from step 5 from the BOTTOM of the riser upwards towards the top of the
6.
riser. Mark a line around the riser, and cut with handsaw, jig saw, or reciprocating saw. Remove debris from cut edge with
scraper, utility knife, or gloves. See Figure 3.
Place cut riser back into ring on unit until it stops. Fasten cover from unit into riser with the same 4 bolts from the unit. Unit
7.
is ready to be water tested and backfilled. Install finished floor. See Figure 4.
NOTES:
Schier grease interceptors are rated and manufactured with an internal flow control system already in
place. They do not require an external flow control system or air intake vent.
Schier grease interceptors are not to be installed in any other manner except as shown. Consult local
codes for separate trapping requirements, cleanout locations and additional installation instructions
TeleGlide Riser (16 Series) Installation Guidelines
(GB-15, GB-20, GB-25)
Minimum and maximum riser heights when units are buried.
DATE:
11/1/10
GREAT BASIN INSTALLATION, OPERATION
AND MAINTENANCE GUIDE
Schier Products
9500 Woodend Rd
Edwardsville, KS 66111
Tel: 800-827-7119
Fax: 800-827-9664
www.schierproducts.com
Made in the U.S.A
DESCRIPTION:
DWG BY:
TEU
REV:
3 - 11/07/11
SHEET NUMBER:
7 of 7
MATL:
PE
THE INFORMATION CONTAINED IN THIS DRAWING IS THE SOLE PROPERTY OF
SCHIER PRODUCTS
. ANY REPRODUCTION IN
PART OR AS A WHOLE WITHOUT THE WRITTEN PERMISSION OF
SCHIER PRODUCTS
IS PROHIBITED.
PROPRIETARY AND CONFIDENTIAL