ELECTRICAL CONNECTIONS 

The following steps (Figure 3) correspond with a low-voltage three phase network: 

1.

 

Make sure all power sources are disconnected. 

2.

 

Make sure that your designated power supply corresponds with the unit's rating. 

3.

 

Connect the power supply (bottom-left of front panel) via 12 AWG wires and a 

designated circuit breaker. 

4.

 

Standard external current transformers: connect the CT's (14 AWG minimum) "

+

" pole to 

the device's 

I1+

 current input (unit’s bottom right of front panel, as in figure 3) and the "-

" pole to the adjacent I1- current input. Repeat this for the following two phases, 

I2

 and 

I3

. Verify proper polarity in your connections in accordance with the arrow printed on 

the external CTs.  

“HACS” CTs: connect the red/white wire to the "

+

" terminal and the black/orange (colors 

vary according to the CT model) wire to the "

-

" terminal. 

5.

 

Connect the voltage measurement inputs (22-12 AWG; bottom-center of front panel). 

6.

 

Connect the com wire (26-12 AWG, shielded) to COM1 (RS485, top-left of front panel). 

7.

 

Power-on the unit. 

Figure 3

: Typical wye installation 

 