To connect a bathtub (or shower), make sure the waste
trap height is raised by at least 15cm above floor level.
Connection must be made using 40mm or 50mm
diameter pipework, with minimum slope of 1%.
The disposal of waste from the Sanicom can discharged through a 32mm diameter copper or plastic pipes (or PVC, ABS, etc.).
This discharge pipe must be designed so as to prevent back-flow from the sewers. See diagram above.
Horizontal discharge pipework should maintain a 1% fall (1cm/M) to the soil and vent pipe. If a vertical rise is required, this must be installed at
the start of the run, before the horizontal section. The horizontal section should then have a minimum 1% fall to the final drain point.
Take care that the discharge valve flap faces the direction of flow.
If the end of the discharge pipework is much lower than the unit, install a riser pipe about 80mm long from the highest point of the discharge
run and fit an air admittance pipe on top (capable of withstanding at least 15psi pressure.) to break the syphon.
The discharge should be connected to a 100mm discharge stack via a strap boss connector.
9. Connection to sanitary ware
10. Connection to soil and vent pipe or drain
150mm min
1%
40mm
32mm
2.5%
2.5%
Summary of Contents for Sanicom FF03-P95