![S&C 2000 series Installation Manual Download Page 22](http://html1.mh-extra.com/html/sandc/2000-series/2000-series_installation-manual_3077334022.webp)
22
S&C Instruction Sheet 716-502
STEP 20.
Perform fi nal checkout as detailed below:
NOTICE
Check the following . Failure to make the
following checks can result to damage to the
circuit-switcher when operated .
(a) At each transition box, make sure:
• The interrupter stop bracket and spacer have been
removed (see Figure 19)
• The transition lever has been connected to the
operating rod link (see Figure 12 on page 17)
• If the optional remote gas-density monitor is
present (catalog number suffi x “-R”) make sure
connections are made according to Instruction
Sheet 716-530
(b) At each interrupter, make sure:
• Both shipping-container halves and all associated
packing and hardware have been removed
• The pressure relief shield has been removed from
the target-end of the interrupter (See Figure 15
on page 19)
Figure 19. Check the transition box and high-speed base for these shipping parts.
Adjustable locking rod
Stop bracket
Spacer
Installation