Switch Setting and Testing Operation
Step 1
Review all the following elements in the installation:
Installation site strength
Piping connection tightness to detect any gas leakage
Connection wiring
Heat-resistant insulation of the piping
Drainage
Earthing wire connection
Step 2
IMPORTANT!
Before selecting switch turn off the system power supply
Step 3
Follow of indication reported into table below for indoor unit addressing
Step 4
Turn on the system power supply and waiting for 60 seconds after
estabilishing communication between outdoor and indoor units.
During this phase, the left display of outdoor unit display PCB “DIS01” will
count fom 00--01--02 to 15.
Estabilished communication the left display will count sequentially:
00--communication with indoor unit A;
01--communication with indoor unit B;
02--communication with indoor unit C;
03--communication with indoor unit D;
To complete the installation, perform the following checks and tests
to ensure that the air conditioner is operating correctly.
COMPLETING THE INSTALLATION
In case of Manual address mode,you can do pipe check operation for check
whether you connect the pipes correctly or not.
But you need set indoor address switch yourselves.
K 1
K 2
K 3
DIS0
1
SW02
SW01
K 4
DIS02
Switch
Indoor unit
address
View data display
K 1
K 2
K 3
DIS0
1
SW02
SW01
K 4
DIS02
Switch
Indoor unit
address
View data display
SW 02
Manual
addressing
Move down the
switch n°1
- Move dipswitch
n°1 of “SW02 -
outdoor unit
display PCB”
down;
SW01
SW01
ex)
connecting
with 2 indoor
units.
ex)
connecting
with 4 indoor
units.
- Select rotary switch “SW01” of outdoor
unit display PCB, according to number
of indoor unit connected:
Advise control we are going to proceeed
with manual addressing as follow: