19
English
Installation Pr
oc
edur
e
4
Using a crimping tool, compress the two points and
flip it over and compress another two points in the
same location.
• The compression dimension should be 8.0.
Compression
dimension
• After compressing it, pull both sides of the wire to
make sure it is firmly pressed.
Compress it 4 times.
5 mm
Method 1
Compress it 4 times.
5 mm
Method 2
5
Wrap it with the insulation tape twice or more and
position your contraction tube in the middle of the
insulation tape.
Method 2
Method 1
Insulation tape
40 mm
Insulation tape
35 mm
6
Apply heat to the contraction tube to contract it.
Method 2
Method 1
Contraction tube
Contraction tube
7
After tube contraction work is completed, wrap it with
the insulation tape to finish.
Three or more layers of insulation are required.
Method 2
Method 1
Insulation tape
Insulation tape
CAUTION
• Make sure that the connection parts are not exposed
to outside.
• Be sure to use insulation tape and a contraction tube
made of approved reinforced insulating materials
that have the same level of withstand voltage with
the power cable. (Comply with the local regulations on
extensions.)
WARNING
• In case of extending the electric wire, please DO NOT
use a round-shaped Pressing socket.
– Incomplete wire connections can cause electric
shock or a fire.