24
EB 8026 EN
Mounting and start-up
5 Mounting and start-up
SAMSON valves are delivered ready for
use. In special cases, the valve and actuator
are delivered separately and must be assem-
bled on site. The procedure to mount and
start up the valve are described in the follow-
ing.
Risk of valve damage due to excessively high
or low tightening torques.
Observe the specified torques on tightening
control valve components. Excessively tight
-
ened torques lead to parts wearing out
quicker. Parts that are too loose may cause
leakage.
Observe the specified tightening torques
(
u
AB 0100).
Risk of valve damage due to the use of un
-
suitable tools.
Only use tools approved by SAMSON
(
u
AB 0100).
5.1 Mounting the actuator onto
the valve
Proceed as described in the actuator docu-
mentation if the valve and actuator have not
been assembled by SAMSON.
Versions with V-port plug
In mixing valves in sizes larger than DN 25,
the bottom plug is designed as V-port plug.
Each V-port plug has three V-shaped ports.
Depending on the valve size, the size of the
symmetrically arranged V-shaped ports var-
ies. The process medium in the valve flows
through the V-shaped ports as soon as the
plug is lifted out of the seat.
1. Before mounting the actuator, determine
which V-shaped port is uncovered first
when the plug is lifted out of the bottom
seat.
Usually, this is the largest V‑shaped port.
2. On mounting the actuator, make sure
that the V-shaped port uncovered first
faces toward the valve outlet (
AB
) at the
side.
Medium flow obstructed due to incorrect
installation of the V‑port plug.
To achieve the best flow conditions inside the
valve, the V‑port plug must always be
installed with the largest port facing toward
the valve outlet.
Make sure the V‑port plug is installed cor
-
rectly.
NOTICE
!
NOTICE
!
Tip
NOTICE
!
Summary of Contents for 3244
Page 11: ...EB 8026 EN 11...
Page 31: ...EB 8026 EN 31...
Page 48: ...48 EB 8026 EN...
Page 50: ...50 EB 8026 EN 81 25 84 83 82 80 32 2 11 12 16 8 10 9 15 7 39 30 33 14 21 23 81 26...