SAMCO CSR Installation Manual Download Page 7

Operation | Priming | Starting | Shutdown

7

OPERATION

PRE-START CHECKS

Before initial start of  the pump, make the  

 

following inspections:

1.  Check alignment between pump and motor.  

2.  In the desired direction, check rotation each  
 

time motor leads have been disconnected.

3.  Check all connections to motor and starting  
 

device with wiring diagram. Check voltage,    

 

phase, and frequency on motor nameplate with  

 

line circuit.

4.  Check suction and discharge piping and 
 

pressure gauges for proper operation.

5.  Turn rotating element by hand to assure that it  
 

rotates freely.

6.  Check impeller clearance.

7.  Assure that pump bearings are properly  

 

 lubricated.

8.  Assure that pump is full of  liquid.

PRIMING

If  the pump is installed with a positive head on the 
suction, it can be primed by opening the suction 
and vent valve and allowing the liquid to enter the 
casing.

If  the pump is installed with a suction lift, priming 
must be done by other methods such as foot 
valves, ejectors, or by manually filling the casing 
and suction line.

NOTE: Under either condition, the pump must be 
completely filled with liquid before starting. The 
pump must not be run dry in the hope it will prime 
itself.

STARTING

1.  Close drain valves.

2.  Fully open all valves in the suction and  

 

 

discharge lines.

3.  If  pumped fluid is dirty, these lines should    
 

always be left open except when using double  

 

mechanical seals.)

4.  Prime the pump.

NOTE: If  the pump does not prime properly, or 
loses prime during start-up, it should be shut down 
and the condition corrected before the procedure 
is repeated.

5.  (Pumps moving high temperature liquids).    
 

Open the warm-up valve to circulate liquid for  

 

preheating.  Close the valve after the pump is  

 

warmed up.

6.  Start the pump driver (turbines and engines  
 

may require warming up; consult the   

 

 

manufacturer's instructions).

7.  When the pump is operating at full speed,    
 

check to see that the check valve has opened  

 

up. Check valve must open 5 seconds or less  

 

after start-up to prevent damage to pump by  

 

operating at zero flow.

8.  Adjust the seal water valves to produce the    
 

recommended pressure for either the  

 

 

mechanical seal or packed stuffing box.

Note: The valve in the discharge line should always 
be closed when the pump is started.  The excessive 
current required by the motor to start under full 
load will in time cause motor trouble. 

SHUTDOWN

The following steps will take care of  most normal 
shutdowns of  the pump. Make any further adjust-
ments of  process piping, valves, etc., as required. 
If  the pump is to be removed from service for an 
extended period of  time, refer to "Storage", and 
"Freeze Protection".

1.  Close the discharge valve slowly.

Note: When stopping pump, always close discharge 
valve first.

2.  Shut down the driver (consult manufacturer’s  
 

instructions for special operations).

3.  Close seal water valves. (If  pumped liquid is  
 

dirty, or if  in leakage is to be prevented, these  

 

lines should always be left open, except when  

 

the pump is completely drained.)

4.  Open drain valves as required.

Summary of Contents for CSR

Page 1: ......

Page 2: ... 7 MAINTENANCE 8 GENERAL MAINTENANCE AND PERIODIC INSPECTION 8 MAINTENANCE TIME TABLE 8 TROUBLE SHOOTING 9 11 NOTE The information contained in this book is intended to assist operating personnel by providing information on the characteristics of the purchased equipment It does not relieve the user of their responsibility of using accepted engineering practices in the installation operation and ma...

Page 3: ...ERIAL NUMBER Composed of certain groups of numbers All groups are necessary for identification TYPICAL EXAMPLE P 2081 98 2 MODEL CSR followed by SIZE Composed of three 3 groups of number EXAMPLE 4 x 3 x 11 First number 4 is the ASA suction flange size in inches second number 3 is the ASA discharge flange size in inches the third number 11 is the nominal maximum impeller diameter in inches 3 IMPELL...

Page 4: ...s condition provides a positive suction head on the pump It is also possible to prime the pump by pressurising the suction vessel When installing the pump consider its location in relation to the system to assure that sufficient Net Positive Suction Head NPSH at pump suction is provided Available NPSH must always equal or exceed the required NPSH of the pump The pump should be installed with suffi...

Page 5: ...n piping observe the following precautions a If the pump is operating under static lift conditions a foot valve may be installed in the suction line to avoid the necessity of priming each time the pump is started This valve should be of the flapper type rather than the multiple spring type sized to avoid excessive friction in the suction line Under all other conditions a check valve if used should...

Page 6: ...sion or corrosion of the shaft or shaft sleeve and rapid packing or mechanical seal deterioration they can even plug the stuffing box flushing and lubrication system The stuffing box must be supplied at all times with a source of clean clear liquid to flush and lubricate the pack ing or seal The most important consideration is to establish the optimum flushing pressure that will keep contaminants ...

Page 7: ...mp NOTE If the pump does not prime properly or loses prime during start up it should be shut down and the condition corrected before the procedure is repeated 5 Pumps moving high temperature liquids Open the warm up valve to circulate liquid for preheating Close the valve after the pump is warmed up 6 Start the pump driver turbines and engines may require warming up consult the manufacturer s inst...

Page 8: ...ings are running hot over 180 it may be the result of too much lubricant If changing the lubricant does not correct the condition disassemble and inspect the bearings Check grease lubricated bearings for saponification This condition is usually incurred by the infiltra tion of water or other fluid past the bearing shaft seals and can be noticed immediately upon inspec tion since it gives the greas...

Page 9: ...on will cause pump damage Dismantle pump or use piping hand hole to clean impeller Not enough liquid delivered 8 Air leaks in suction piping 9 Air leaks in stuffing box 10 Speed too low 11 Discharge system head too high 12 Suction lift too high 13 Impeller partially plugged 14 Cavitation insufficient NPSH depending on installation 15 Defective impeller 16 Defective packing If liquid pumped is wate...

Page 10: ... enough pressure 21 Speed too low 22 Air leaks in suction piping 23 Mechanical defects 24 Obstruction in liquid passages 25 Air or gases in liquid Test in laboratory reducing pressure on liquid to pressure in suction line Watch for bubble formation 26 Excessive impeller clearance 27 Too small impeller diameter probable cause if none of the above See item 5 See item 8 See items 15 16 and 17 Dismant...

Page 11: ...See item 14 See items 15 16 and 17 See item 18 Use larger driver Consult factory for recommended size Test liquid for viscosity and specific gravity See item 6 Release gland pressure Tighten reasonably If sealing liquid does not flow while pump operates replace packing If packing is wearing too quickly replace scored shaft sleeves and keep liquid seeping for lubrication Check alignment Examine pum...

Page 12: ...SAM Engineering Pty Ltd 24 Duncan Road Lilianton Boksburg South Africa Tel 27 0 11 823 4250 Fax 27 0 11 823 4943 Email pumps sameng co za www sameng co za ...

Reviews: