COMMISSIONING
6.1 Start Up and Shut Down the Energy Storage System
6.1.1 Start Up
Step 1: Turn on the circuit breaker
Step 2: Press and hold the main switch for 2-3s
,
until the display is on
6.1.2 Shut Down
Step 1: Press and hold the main switch for 5s, until the display is off
Step 2: Turn off the circuit breaker
Figure 6.1
Circuit breaker of inverter
Figure 6.2
Start button of inverter