INSTALLATION INSTRUCTIONS

The first TempLink 3000 must be positioned in a location safely reached by a secured ladder or a manhole access point.
 Access to inside the roof space is not required for installation purpose’s.
The building structure must be inspected for integrity and compliance in relation to relevant building codes.
The building construction must meet all requirements in regard to correct fitting and use of materials set by manufacturers. 
Inspections must be undertaken of timber and metal structural components for signs of structural damage such as splits, water 
damage, pest erosion and fixing issues.
Roof spaces to be accessed must not be over 30 degrees in pitch.

Metal Roof Sheeting with Metal Battens or Timber Battens

It is recommended the TempLink 3000 be installed to the crest of the roof sheeting  profile, where this is not practical the   
TempLink 3000 may be installed into the pan away from debris.
Metal roof sheet size must be a minimum of 0.42mm.

1. 

Remove six (6)  of the existing roof screws along the batten line at the appropriate location for the TempLink 3000.

2. 

Place the cable section out along the roof sheeting, adjust the tabs to fit the roof profile and to line up with the existing 

             roofing screw holes.  
3. 

Replace the six existing roofing screws with six (6) screws Size 14(g) -10(TPI) x 65 Hex Head Screws. Screw through each 

             tab and existing hole, securing to the batten under the roof sheeting.
                    

     

             DO NOT OVER TENSION SCREWS AS THIS WILL RESULT IN THREAD STRIPPING, TAB / STRUCTURAL DAMAGE.

4. 

Ensure the screws are the correct length to engage the batten to eliminate over passing the thread into the blank part of 

             the screw.  Screws must penetrate timber batten by at least 35mm.

Tile Roof with Timber Rafters

1. 

Remove existing roof tiles at the appropriate location for the TempLink 3000.

2. 

Place the cable section down the rafter and drill a 4.5mm pilot hole, (never attach to battens on tile roofs, always only attach 

             to suitable rafters). 
3. 

Screw tabs to the rafter through the tab holes no less than 100mm apart using six (6) x Size 14(g) -10(TPI) x 65, Hex Head   

             Screws.  

             DO NOT OVER TENSION SCREWS AS THIS WILL RESULT IN THREAD STRIPPING, TAB / STRUCTURAL DAMAGE.

4. 

Screws must penetrate timber batten by at least 35mm.

The SafetyLink TempLink 3000 anchor point is now ready for use, giving you an anchor point to attach to while installing the next 
SafetyLink anchor point.

Removal of 

TempLink 3000

During removal you must ensure you are safe at all times.

1. 

Remove screws from the TempLink 3000 and remove TempLink 3000.

2. 

On tiled roofs replace the tiles and ensure a water tight seal is achieved.

3. 

On metal roofs replace the six (6) x Size 14(g) -10(TPI) x 65, Hex Head Screws to secure roof sheet and ensure a water 

             tight seal is achieved.

TIMBER / METAL

TIMBER / TILE

Summary of Contents for TempLink 3000

Page 1: ... not be left unattended or exposed to the elements for prolonged periods of time It is recommended that the TempLink 3000 be uninstalled when not in use and stored in its bag in a safe clean and dry environment free from chemicals and UV light Installation must be carried out by or under the supervision of a competent person Users of fall arrest equipment and all people undertaking tasks associate...

Page 2: ...uctions Inspect the cable and tabs joining position for signs of wear Inspect the remove from service date on product the shelf life of this product does not exceed 10 years The TEMPLINK 3000 anchor point has one energy absorbing stainless steel component If this energy absorbing region is expanded distorted this will indicate the anchor point has arrested a fall and should be removed from service...

Page 3: ...six 6 screws Size 14 g 10 TPI x 65 Hex Head Screws Screw through each tab and existing hole securing to the batten under the roof sheeting DO NOT OVER TENSION SCREWS AS THIS WILL RESULT IN THREAD STRIPPING TAB STRUCTURAL DAMAGE 4 Ensure the screws are the correct length to engage the batten to eliminate over passing the thread into the blank part of the screw Screws must penetrate timber batten by...

Page 4: ...ection shall be withdrawn from service immediately and a replacement obtained if necessary A label indicating the condition or defect should be attached to the equipment and it should be examined by a competent person who will decide whether the equipment is to be destroyed or repaired if necessary and returned to service In the latter case details of any repair shall be documented and a copy give...

Reviews: