9
S
ection
2 — A
SSembly
& S
et
-U
p
Figure 3-5
Removing the Log Dislodger and Tray
6.
Disconnect the dislodger from the beam weld bracket by
removing the six hex screws. See Figure 3-6.
Hex Screws
Hex Screws
Dislodger
Figure 3-6
7.
Disconnect the log tray from the beam on the side of the
control valve by removing the two hex washer screws that
secure it to the beam and the two hex washer screws in the
beam. See Figure 3-7.
Hex Washer
Screw
Log Tray
Beam
Figure 3-7
Positioning the Cylinder
8.
Lift and slide the cylinder up to the top of beam and into
the weld brackets. See Figure 3-8.
Cylinder
Weld Brackets
Figure 3-8
9.
Reattach the dislodger over the wedge assembly and
secure it to the weld brackets with the previously removed
hardware. See Figure 3-6.
NOTE:
Lift up on the cylinder when installing the hex
screws.
NOTE:
Once the six hex screws are tightened, there may be
a slight gap between the dislodger and the weld brackets.
This gap is normal.