Step 2 - Fixing Wall Profile
1. Drill three 4.5mm holes into the U-Channel on the Wall Profile, approximately 100mm from each end and
the last one positioned in the centre.
2. Position the inside edge of the Wall Profile onto the pencil mark you have just made.
3. Make sure the Wall Profile is vertical using a spirit level.
4. Using a pencil mark the locations for the drill holes through the holes of the Wall Profile.
5. Drill the holes using a 6mm masonry drill (not supplied); push the wall plugs (supplied) into the drilled
holes.
6. Apply a bead of sealant the width of the Wall Profile at the bottom where the Wall Profile meets the tiled
wall.
7. Screw fix the wall profile to the wall using the 40mm screws (supplied) ensuring it is vertical.
8. Apply a bead of sealant to the inside of the Wall Profile at the bottom where it meets the Bath top.
• IMPORTANT: The Wall Profile must be completely vertical (the bubble should be in the centre of the 2
lines on the spirit level). The sealant must be applied in steps 6 and 8; failure to follow out this procedure
may result in serious water damage and is not covered under the terms of the guarantee.