Service
R&S
®
ESH3-Z6
19
Manual 1178.9932.02 ─ 01
1
1.5
2
100
kHz
150
kHz
100
MHz
200
MHz
[dB]
Figure 5-7: Limits for voltage division factor X2 - X3
5.2.5
Reflection VSWR of X3
Test equipment
●
Vector network analyzer
●
BNC 50
Ω
terminator
●
2x adapter Xn - BNC-F
Preparing the EUT
1.
DANGER!
Do not connect the R&S
ESH3-Z6 to mains voltage for the test. Con-
necting the R&S
ESH3-Z6 to the mains voltage poses hazardous or even life-
threatening risks to the operator.
Arrange the test setup as shown in
.
2. Install the Xn - BNC-F adapter on X1 and X2 connectors.
3. Tighten the torque of M8 nuts: 8
Nm to 10
Nm.
4. Connect the BNC 50
Ω
termination to the BNC adapter installed on X2.
5. Connect the Port 1 to the X3 connector.
VNA
Port 1
Port 2
Short
R&S ESH3-Z6
X2.1
X2.2
X1.1
X1.2
X3
50
Figure 5-8: Test setup for VSWR of X3
Perfomance Test