20
2
3
7
INSTALLATION
The installation must be performed by qualified and experienced personnel,
in full compliance with the regulations.
For General instructions for installation and maintenance, refer to section
3 of this installation manual.
7.1) Preparation and installation of the foundation plate
The following illustrations are for illustrative purposes only, as the space
for securing the automation and the accessories varies depending on
the dimensions. It is therefore the installer who selects the most suitable
solution for analysing the spaces and the surrounding environment, ensure
that there are no impediments to the movement of the bar, such as trees,
electricity cables, street lights or other things and carefully selecting the
most suitable automation for installation to be carried out, based on the
width of the passage and the limits of use.
Assemble the 4 anchors complete with nuts; warning: the lower nut must
be screwed to the end of the thread, so as to comply with the "Z" minimum
height of 40 mm as shown in
Fig.2.
Run the foundation hole with the
following minimum dimensions: one metre by one metre and a depth of 0.3
metres, to accommodate the "KT230" foundation plate, as shown in
Fig 3.
Position the conduit for the passage of the electric cables.
Perform an adequately reinforced concrete cast with iron cages, flood the
central foundation plate so it is flush with the surface, perfectly level and
parallel to the structure of the barrier and the bar, which is to be installed
later, after the concrete is completely set, as shown in
Fig. 3.
The concrete foundation must be made following the standard rules, by
competent personnel.
7.2) Installing the barrier assembly
After successfully laying the foundation plate (7.1), install the body of the
barrier.
Remove the washers and nuts screwed onto the tie rods on the "
KT230
"
foundation plate that was previously cemented, as shown in
Fig 4.
Unscrew the 2 screws fixed on the head of the case, on the side where the
bar is to be fixed, as shown in
Fig 5.
Open the inspection door through the appropriate lock by turning the key
90° clockwise, as shown in
Fig. 6.
Manually lift the head, disconnect the grounding cable dedicated to the
head from the concentrator; support the head on a suitable surface so as to
avoid impacts or electrical damage.
After also disconnecting the grounding cable dedicated to the inspection
door from the concentrator
(Fig.
7),
it is possible to open the door by
removing it from its slot.
Support the case on top of the "KT230" foundation plate so that the
cemented tie rods pass through the 4 slotted holes located in the 4 corners
of the base.
Insert the washers and nuts that were removed onto the tie bars, as shown
in
Fig. 8;
orient the case as desired, using the slots of the base and then
tighten the nuts firmly for the barrier body case in a stable manner.
Important Note:
In terms of electronics, the barrier is set in the factory for installation on
the right (
DX
), when looking at the gate from the inside. In the event that
installation is to be done on the left (
SX
)follow the instructions given in the
bar assembly section.
Summary of Contents for Agilik AG/004
Page 7: ...7 4 5 6 7 8 ...
Page 21: ...21 4 5 6 7 8 ...
Page 35: ...35 4 5 6 7 8 ...
Page 49: ...49 4 5 6 7 8 ...
Page 63: ...63 4 5 6 7 8 ...
Page 77: ...77 4 5 6 7 8 ...
Page 87: ...87 ...