Rockwell Automation Publication 2100-IN012D-EN-P - September 2010
71
Chapter
7
Final Checklist Before Energizing
Introduction
This section provides guidance for the startup of a newly installed MCC.
We recommend making an itemized list including:
•
serial number.
•
number of sections.
•
number of units and their corresponding voltage.
•
current ratings.
•
horsepower ratings
•
types of circuits.
•
fuse sizes.
•
circuit breaker ratings and trip settings.
•
heater elements requirements.
•
arc resistant components.
•
other important data.
The itemized list could be modeled after the MCC layout drawings supplied with
each MCC. This itemized list should be saved in a file along with other data for
the MCC such as, component manuals, heater element instructions, MCC
manuals, and wiring diagrams. Blank sample forms are provided at the end of this
chapter.
Pre-energizing Check
Procedure
The following procedures should be executed by a ‘qualified person’ as defined by
NEMA Standards Publication / No. ICS 2.3, Instructions for the Handling,
Installation, Operation and Maintenance of Motor Control Centers, Section 1 as
follows:
1.4 Qualified Person
For the purpose of this guide, a qualified person is one who is familiar with
the installation, construction and operation of the equipment and the
hazards involved. In addition, he or she has the following qualifications:
1.4.1 Is trained and authorized to energize, de-energize, clear, ground and
tag circuits and equipment in accordance with established safety practices.
1.4.2 Is trained in the proper care and usage of protective equipment such
as rubber gloves, hard hat, safety glasses or face shields, flash clothing, etc.,
in accordance with established safety practices.