8

 

A Lead/Lag system sequences the on-off firing of multiple boilers to meet the system load demand and equalize run 
time for all the boilers in a system. 
 
The key to the design of a lead/lag control in a hot water system is the control intelligence to react to changes in system 
load which are inherently slow without over reacting. The change in boiler output does not immediately result in a 
change in overall system temperature. The control system must be designed to take into account the lag times and allow 
for fine tuning. 
 
The TempTrac

®

 control is designed to optimize the operation of the EMBLEM

®

 system in order to provide the maximum 

efficiency of operation. When interfacing a Lead/Lag system with multiple EMBLEM

®

 systems 

DO NOT

 attempt to 

interrupt the independent operation of this control. There are three options on the following page which will allow 
Lead/Lag and Outdoor Reset control of the EMBLEM

®

 system, while maintaining optimum efficiency.  

 
 

LEAD/LAG CONTROL OPTION 1: (Recommended) 

The lead-lag and outdoor-reset control is accomplished by the on-board TempTrac

®

 controls. The TempTrac

®

 control 

has a 7day real time clock which in conjunction with a programmable set-back schedule will alternately reduce the 
control set-point by a programmed set-back temperature. The following is an example of a 3 boiler lead-lag schedule: 
 
 

Objective

: Balance operational time evenly between all EMBLEM

®

 

boiler systems. 

 

Parameters

:  E1-E7, S1-S7, Sb1-Sb7 

  The E series parameters are the starting point for the programmed shift in set point. The E series 

parameters are divided into 10 minute increments. The E1 parameter is Sunday.  

  The S series parameters are the ending point for the programmed shift in set point. The S series 

parameters are divided into 10 minute increments. The S1 parameter is Sunday.  

 

The Sb series parameters are the shift in set point imposed for the time period defined by E and S. The 
shift in set point can be (-40Fto40F). The Sb1 is Sunday. 

Programming

: The TempTrac

®

 boiler control located on the 

PRIMERA

®

 allows for one button access to this 

menu. Hold down the up button

ES

 

until E1 appears in the top display. The up/down arrow buttons will now 

scroll through this menu. When you have reached the desired parameter, push the set button 

 

in order to 

enable adjustment and the up/down buttons to change the set point. Push the set button to lock in the value. 
See the TempTrac

®

 Service & Setup Manual (34-81), for addition information on programming.

 

 

 

Example: A 3 boiler hydronic heating system, with a supply target temperature of 165 F. In this case lead 
operation will be divided 3 ways in to a 24 hour day.  
 

 

Boiler #1 St1=160, E1=0.0, S1=8.0, Sb1=5 

 

Boiler #2 St1=160, E1=8.0, S1=16.0, Sb1=5 

 

Boiler #3 St1=160, E1=16.0 S1=24.0,Sb1=5 

 

 

Boiler #2 St1=160, E2=0.0, S2=8.0, Sb2=5 

 

Boiler #3 St1=160, E2=8.0, S2=16.0, Sb2=5 

 

Boiler #1 St1=160, E2=16.0, S2=24.0,Sb2=5 

 

 

Boiler #3 St1=160, E3=0.0, S3=8.0, Sb3=5 

 

Boiler #1 St1=160, E3=8.0, S3=16.0, Sb3=5 

 

Boiler #1 St1=160, E3=16.0, S3=24.0,Sb3=5 

 

The above example would designate the lead boiler by advancing the set point of one boiler by 5 deg F. The 
same result could be produced by reducing the set points of the 2 lag boiler. In this case Sb1= -5 deg F. 

 
 

 

 

Riverside Hydronics

®

, LLC  -  990 Haltom Road  -  Fort Worth, Texas  76117  -  Tel 1-800-990-5918

 

 

Sunday 

Monday 

Tuesday 

Summary of Contents for Emblem

Page 1: ...structions must be given to the equipment user or left near the appliance Refer to I M documents 34 50 34 501 and 34 502 for additional important information SPECIAL INSTRUCTIONS TO THE OWNER Retain t...

Page 2: ...res are high the EMBLEM system engages a non condensing boiler to supplement heat output Although non condensing the secondary boiler in the EMBLEM system still operates at relatively high efficiency...

Page 3: ...n from the system water to be heated to the Inlet of the EPV boiler Connect the Outlet to the supply side of the system hot water out of the unit FILLING THE UNIT 1 Fill the system with water To be su...

Page 4: ...1 St1 parameter is the first to be displayed Press the Set key again and adjustment is enabled Use the arrow keys to adjust the set point 1 to the desired system temperature and press the set key agai...

Page 5: ...the inherent flexibility of the EMBLEM system The Primary Only System is generally not applied with modern PRIMERA boiler systems due to the need to maintain a constant flow rate through the boiler Th...

Page 6: ...6 Riverside Hydronics LLC 990 Haltom Road Fort Worth Texas 76117 Tel 1 800 990 5918...

Page 7: ...t always the case Untreated make up water is a leading cause for failures of hat water boilers Provisions must be made for properly introducing metering and treating make up water Below are some consi...

Page 8: ...he E series parameters are divided into 10 minute increments The E1 parameter is Sunday The S series parameters are the ending point for the programmed shift in set point The S series parameters are d...

Page 9: ...1 160 E2 0 0 S2 6 0 Sb2 25 LEAD LAG CONTROL OPTION 2 The lead lag and outdoor reset function is managed by a third party Boiler Management System BMS or building Energy Management System EMS This mann...

Page 10: ...ata Function Code Code of the desired function 0X06 Register Address The address of the first register to be read Set point 1 St1 has a register address of 768 Data The data to write CRC Defines the C...