NOTE: Curtain guides are rough placed at this point,
and will need to be set in proper position
later.
1. Floor space the size of the unit is required for
installation
2. Remove the curtain container (A) from the crate and
position in front of the machine (B) with the bottom
braces toward the weld unit,
Figure 3.1.
3. Remove curtain container cover toward weld unit
facing up.
4. Remove header guides and position them next to
the curtain container. Groove w/o tabs (C) toward
the top on right side. Groove with tabs (D) toward
the bottom on left side. Non-drive side w/Interrupt
switch will be 4” [102] longer.
5. Loosen the 1/4” [6] bolts and nuts (E) on the
container,
Figure 4.1.
6. Slide the “T” nuts (F) into the groove on the header
guides and place flush (G) with the bottom of the
curtain container and tighten all bolts. In special
ordered situations the curtain container may need to
be mounted some pre-determined distance of the
floor,
Figures 4.2 & 4.3.
8. Locate the mounting brackets supplied in the parts
box, and assemble brackets to the header guides
with the required 1/4-20 [6] bolts and “T” nuts,
Figure 4.4.
Brackets may be turned 90° for
mounting to wall or weld unit.
Floor mount bracket for both sides of header guides
(H).
Single outside floor mount bracket (I).
9. Attach the belting pressure plate (J) to the idle belt
attachment bracket with the (2) 1/4-20 x 3/4” [6x19]
bolts and lock washers provided,
Figure 4.5.
Repeat on non-drive side.
10. Install idle belt attachment bracket on the inside of
the drive header guide flush with the bottom, using
two 1/4-20 x 3/4” [6x19] bolts and “T” nuts,
Figure
4.5.
11. Tip both header guides to stand unit up.
PUB. NO. FLSFLDG SEPTEMBER 2015
5
CHAPTER 2 - GUIDE INSTALLATION
A
Figure 3.1
B
D
C
Figure 4.3
Figure 4.1
Figure 4.2
E
F
G