rev.00 - 11
GB
Assembly instructions
400
Concrete
C25/30 grade
Ø 50mm
Corrugate
Pipe
Drainage pipe Ø100mm min.
Terbond
nonwoven
200
1/2 Sand
1/2 Drainage
Gravel
800x800mm
40 l
800x800mm
W
7 - If the water takes more than 25 minutes to be absorbed by the
ground, it will be necessary to proceed with the laying of pipes to convey
water in a tub and possibly aspire it by an electric pump.
8 - Insert the foundation case in the excavation.
Attention: The case must rest on the bottom of the excavation and
must be perfectly vertical - check this by placing a level on the upper
flange
.
Important: In order to make inserting the case easier, preparation for the
corrugated sheath must be 200mm from the flooring surface, as shown
in figure.
Insert the 50 mm diameter corrugated sheath in the case using the metal
guide.
The corrugated pipe must enter a maximum of 2/3 cm inside of the metal
protection, so that it does not interfere when the bollard is later inserted.
Provide the layer of gravel. Provide the layer of sand
Roll over the entire surface a layer of polyester fiber nonwoven type “Ter-
bond”
Use the following composition of concret to cement the foundation case:
- Minimum content of cement 300kg/metro3.
- Concrete type CEM III-IV
- Max. supply water/concrete = 0,6
- Exposure class XC2
- Max diameter of aggregating = 32mm
Attention: Make sure, during the cast, that the fixing plug located un-
der the cramp-iron is completely covered by concrete. Using a spirit
level, check if the flange plane is horizontal
.