![Rinnai Brivis AD Series Installation Manual Download Page 13](http://html.mh-extra.com/html/rinnai/brivis-ad-series/brivis-ad-series_installation-manual_1462365013.webp)
Brivis 13
Evap AC IM
6. INSTALLATION - BRIVIS ADVANCE
6.1 BRIVIS ADVANCE SERIES DROPPER DUCT SPECIFIC
•
All Brivis Advance Series units sit on a 550mm x 550mm dropper box with a
15-20mm out turned flange.
•
Brivis Advance Series units can also be installed on an existing dropper
box� Ensure the dropper box is in a sound condition and the top of the
dropper box is level�
•
Brivis Advance Series units may also be installed using a dropper box
transition piece (refer to Sales Department)�
•
The dropper box
MUST BE
positioned as shown on the diagram (right)�
•
Secure the dropper duct vertically, so the Cooler is level when placed on
top of it�
•
Ensure the 3 pin power supply plug and lead, the Wall Control Loom
connection lead, and the rubber grommet, are fed to the inside of the
dropper duct�
•
Cut a 43mm hole in the dropper duct below the roof line, on the left-hand-side
on the low side of the roof, to accept the wiring grommet� This will allow
the 3-pin plug and lead, and the Wall Control Loom connection lead to be
withdrawn from the dropper into the roof cavity�
6.2 FITTING THE BRIVIS ADVANCE UNIT
•
The Brivis Advance Series Cooler chassis comprises latching brackets to secure the unit to the dropper box� To
assist with connection it is important the dropper box has a 15-20mm outward turned flange.
•
In addition to the latching brackets the unit
MUST BE
secured to the dropper box and the cooler chassis with
screws, refer below for method:
1� Fold the end of all four latching brackets in towards the dropper box�
2� Using the 5mm hole in the bracket as a guide secure with 8g stainless steel screws�
High side of roof
Cut hole in this position
using 43mm hole saw
below roof line to accept
wiring grommet in this
corner (closest to Cooler
Control Box)�