Burn-in Test
After repairing each unit, a burn-in test is necessary.
In a burn-in test, the lamp is turned on for a set period of
time (such as 50 minutes), then off for another set period of
time (such as 10 minutes).
This can be accessed in the service mode.
For the procedure, see ‘System Maintenance – Functional
Tests
– Burn-in Test’ in the service manual.
The lamp on and off durations can be set before starting the
test.
This procedure takes a number of hours to complete, so
should not be done at the customer site.
After a normal repair: 2 hours
If the cause of the malfunction cannot be detected: 4 hours
After solving a problem that causes the power to
automatically turn off: 6 hours
Summary of Contents for KW5708
Page 1: ...Slide 1 Y0AS Y0AT Y0AV Y0AY Y0AZ Y0B0 Y0BC Service Training Mizar PJ2 Version 1 0...
Page 10: ...Slide 10 10 Overview External View...
Page 11: ...Slide 11 11 Overview Connection Ports...
Page 12: ...Slide 12 Operation Panel...
Page 17: ...Slide 17 Service Training Basic Points about Service...
Page 22: ...Slide 22 LED Display...
Page 27: ...Slide 27 Replacing the Color Wheel Avoid touching the glass parts of the color wheel...
Page 29: ...Slide 29 Rod Adjustment Adjust if there are yellowish or bluish parts in the image...
Page 32: ...Slide 32 Service Training Updating Firmware...
Page 35: ...Slide 35 Background Information Types of Projectors...
Page 42: ...Slide 42 Background Information Polarization...
Page 47: ...Slide 47 Background Information Terms and Definitions...
Page 59: ...Slide 59 Throw Ratio Throw Ratio PD SW...
Page 61: ...Slide 61...