background image

RoughDeck FXB

2

Visit our website 

www.RiceLake.com

1.2 Scale Components

The RoughDeck FXB has six major components as shown in 

Figure 1-1

. Those components and their descriptions are listed in 

the following table.

Figure 1-1. RoughDeck FXB Parts Breakout Diagram

Table 1-1.  RoughDeck FXB Scale Components

Item No.

Component

Description

1

Top Plate

A rigid welded frame unit with a removable deck plate upon which weight is placed; the applied load is 

transmitted from the weigh platform, to the load bridge, to the levers, and then to the load cell

2

Deck Frame

Supports the top plate

3

Load Cell

Electronic force measuring device mounted in a corner of the scale and rigidly fixed to the load bridge structure. 

Wire rope runs from one end of the load cell to the tip of the primary lever

4

Flexure Plates

Flat, high-strength thin plates that transmit the load forces due to the weigh applied to the platform and to the 

lever system. The flexures provide maintenance free pivot point that supports the levers from the base and trans

-

mits forces from the load bridge to the levers and on to the load cell

5

Load Bridge

Two pieces of tubing or channel iron, one on either side of the scale and tied together by two cross members. 

The weigh platform is supported by the load bridge through four platform support pipes. The load bridge is sus

-

pended from the lever system through the load flexures

6

Base Frame

A rigid one piece, welded unit that supports the remaining scale system. The fulcrum flexure support stands are 

welded directly to the base frame

1

2

3

4

5

6

Top Plate

Deck Frame

Load Bridge

Load Cell

Base Frame

Flexure Plates

Summary of Contents for RoughDeck FXB

Page 1: ...RoughDeck FXB Flexure Lever Floor Scale Installation Manual April 6 2020 PN 32958 Rev C...

Page 2: ...marks of their respective companies All information contained within this publication is to the best of our knowledge complete and accurate at the time of publication Rice Lake Weighing Systems reserv...

Page 3: ...troduction 1 1 1 Safety 1 1 2 Scale Components 2 1 3 Operating Requirements 3 1 4 Flexure Lever Operation 3 2 0 Installation 4 2 1 Unpacking the FXB 4 2 2 Inspecting the RoughDeck FXB 5 2 3 Site Prepa...

Page 4: ...RoughDeck FXB ii Visit our website www RiceLake com Rice Lake continually offers web based video training on a growing selection of product related topics at no cost Visit www ricelake com webinars...

Page 5: ...ation that if not avoided will result in death or serious injury Includes hazards that are exposed when guards are removed Indicates a potentially hazardous situation that if not avoided could result...

Page 6: ...ope runs from one end of the load cell to the tip of the primary lever 4 Flexure Plates Flat high strength thin plates that transmit the load forces due to the weigh applied to the platform and to the...

Page 7: ...orizontal Load Cell Excitation Rated Excitation 10 VDC Maximum Excitation 15 V Safe Static Overloading Capacity Maximum 150 of the scale capacity Temperature Compensated range 0 to 150 F 18 to 65 C 1...

Page 8: ...ck frame together and use eye bolts to lift depending on its size 3 Lift scale base from the wooden pallet by connecting eye bolts not included into threaded holes in the side channels of the scale Fi...

Page 9: ...e scale and the indicator must be protected against crushing cutting or moisture damage Protect the cable by running it in conduit Do not allow the cable to lay in water For proper operation the scale...

Page 10: ...op of the cell 6 Screw the short threaded end of the wire rope through the bottom of the load cell until it s flush with the top The weigh platform frame and scale base are marked on the corner near t...

Page 11: ...errors when the scale is loaded 14 Screw the strain relief fitting into the side of the base 15 Route the load cell cable through the strain relief fitting Verify that the cable is not touching any p...

Page 12: ...ed to step 3 3 Remove the deck plate and weigh platform frame 4 Loosen all check link mounting bolts Figure 1 1 on page 2 5 Loosen the top and bottom load flexure gripper plate bolts on the corner to...

Page 13: ...specified centers with one channel extended 12 and equipped with a bolt on pipe stand weight indicator column The weight indicator display is 54 above the floor For models larger than 48 x 60 consult...

Page 14: ...Ground shield not connected to cannon plug or meter shield Loose connection in the junction box Non linear Weight Reading Center flexure is offset from the center line Damage to the load cell Misalign...

Page 15: ...he new load cell to approximate position it was in the old cell 6 Insert the wire rope into the nose iron hold and turn the lower nut on loosely 7 Hold flat washer in place and screw flathead bolt int...

Page 16: ...RoughDeck FXB 12 Visit our website www RiceLake com...

Page 17: ......

Page 18: ...anada Mexico 800 321 6703 International 715 234 9171 Europe 31 0 26 472 1319 Rice Lake Weighing Systems is an ISO 9001 registered company Rice Lake Weighing Systems Specifications subject to change wi...