7

Excessively long cable connections are not good practice. Try to keep these lines to a minimum to

reduce system voltage drop.
BATTERY (+B) & 0V

These 2 connections are to be connected to the battery.

• Ensure that the battery is connected with the right polarity. Although reverse polarity will

not harm the battery, power supply or the load, no backup of the load will occur during a

power outage.

• Consult battery manufactures data before use with the power supply.

• Excessively long cable connections are not good practice. Try to keep these lines to a

minimum to reduce system voltage drop.

RELAY

The 2 relay connections are the floating alarm relay contacts.

• Connect these pins to any circuit, which is required to be activated by an alarm

condition. The 2 pins become shorted when an alarm condition occurs.

• These pins must not be connected to mains circuits or any other hazardous voltage

circuits.

Cabling

AC Cabling: A cable size of 0.75 mm2 (1 8AWG) is recommended.

DC Cabling: A minimum cable size of 1 .5 mm2 (1 6AWG) is recommended.
Note, maximum size of cable to output connector is 2.5 mm2 or 1 2AWG

DC load cables must be sized to carry the maximum full load current and not exceed the system

volt-drop requirements.

Connection

The requirements for wiring a SME240-1 2-20 into a system are as follows:

LOAD (+L) & 0V

These 2 connections are the DC output of the power supply. These connections are to supply the

load.

• These connections cannot be paralleled with output of duplicate power supply for

increased current output.

• The load connection must not be directly connected to the battery or paralleled with the

battery connection. This will disable the battery low voltage disconnect circuit and defeat

the internal battery fuse.

Voltage Setting

When the PSU is turned on without the battery connected to the battery terminals, the output

voltage may be adjusted within the range specified in table 2.

The output voltage adjustment is achieved in the following way:

• Remove any device from the SMBUS data pins and disconnect any battery.

• To increase the output voltage, short the SMBDATA pin (pin 5) to SMBUS0V (pin 4).

The output voltage will increase by approximately 0.1 V/s

• To decrease the output voltage, short the SMBCLK pin (pin 6) to SMBUS0V (pin 4). The output

voltage will decrease by approximately 0.1 V/s
If a battery is connected, the output voltage will revert to the battery voltage setting.

Summary of Contents for SME240-1 2-20

Page 1: ...SME240 12 20 Owner s Manual...

Page 2: ...unting 5 Installation 6 Mounting Options 6 Connectors 6 Alarm Temperature Sensor 6 DC Power Output 6 Connection 7 Cabling 7 Voltage Setting 7 Cooling 8 Specifications 8 Approvals 9 Copyright RFI 2011...

Page 3: ...nnector Flexible mounting options Full protection for the power supply load and battery Local technical support 1 Safety Correct installation is the most critical factor in ensuring the safe use of th...

Page 4: ...very from short circuit is provided with no current tailing in short circuit operation Over voltage protection provides shutdown of power supply Inrush Surge limiting at turn on OTP over temperature p...

Page 5: ...Other fault conditions Battery Charging Operational requirements Trickle Charge When mains is present but the battery voltage is below the LVD Connect voltage the battery is trickle charged circuit th...

Page 6: ...onnected backwards The battery circuit breaker has tripped The relay contacts are rated for 200 mA 60 Vdc Led Indicator Note The Battery Output is derived directly from the Load output Its loading req...

Page 7: ...sure includes 4 x M3 threaded inserts on the bottom surface to allow the unit do be screwed to a mounting bracket Centres are located at 186 5mm x 63mm spacing Feet The SME240 12 20 has 4 x feet posit...

Page 8: ...to suit all types of installations The maximum thread length for these screws is 4 mm from the outside edge of the power supply Hazardous Voltages exist within the power supply so it is important tha...

Page 9: ...DC load cables must be sized to carry the maximum full load current and not exceed the system volt drop requirements Connection The requirements for wiring a SME240 12 20 into a system are as follows...

Page 10: ...pply has inbuilt thermal cooling to maximuse fan life Please ensure that there is no restriction to the venting of the unit Approval Marking Status ACMA C Tick Yes NSW Fair Trading Approval Number U20...

Page 11: ...021478 DOC BCE282 Series User Manual B...