background image

Manufactured by Reynolds Building Systems, Inc.

205 Arlington Drive

Greenville, PA   16125

724-646-3775

This manual is copyrighted. Under the copyright laws, this manual
may not be copied, in whole or in part, without consent from Reynolds
Building Systems, Inc.

©  Copyright 2008

January 19, 2008

Assembly Book

the Ashbury

8' x 12'

Sheds

EZ

EZ

up

Summary of Contents for EZ up Sheds Ashbury

Page 1: ...e Greenville PA 16125 724 646 3775 This manual is copyrighted Under the copyright laws this manual may not be copied in whole or in part without consent from Reynolds Building Systems Inc Copyright 2008 January 19 2008 Assembly Book the Ashbury 8 x 12 Sheds EZ EZ up ...

Page 2: ...ard any material no matter how small until your building is complete Anything leftover may have been used as packing blocking If you encounter any problems while erecting your building call our customer service department at 800 245 1577 If you run into a problem you cannot resolve my home phone is 724 588 9146ET Before you begin construction study this assembly manual Also obtain a building permi...

Page 3: ... long treated floor joists between the 48 long boards Use 16d galv deck nails 5 Install an OSB flooring panel over the floor frame Use 8d spiral deck nails space nails 12 apart 1 After removing all material from the pallet floor turn the pallet over 2 Remove the 2x4 4 shipping cleats 2x4 87 Floor joist 2x4 48 Board 5 8 Flooring ...

Page 4: ...down Nail the floor sections together with 16d galv deck nails 2x4 72 Treated Board 9 Turn floor over and level with bricks or similar material 8 Install 72 long treated 2x4s over the floor joist to reinforce where the floor sections butt together Install the 2x4s 12 from the outside of the floor ...

Page 5: ... assemble 4 four more trusses 5 Apply another wood gusset to the opposite side of the trusses Use 7d sinkers Building Tip To aid in the assembly of the trusses temporarily screw 2x4 blocks to the back wall frame There are short 2x4s that may have an angle on one end supplied in the kit for this purpose This will trap the truss parts and insure that all the trusses will be assembled the same Use 2 ...

Page 6: ...ge The last panel will also extend past the wall frame Install siding with 7d galv nails Space nails 9 apart Siding Extends 3 4 Below Plate LAP Edge 1 Position 2x4 68 1 2 boards together and indicate with X marks where the wall studs will be located Mark the ends that will butt together with the letters A and B 32 1 2 Tie Plate 32 1 2 Tie Plate 72 Tie Plate LAP Edge 2 Install 44 wall studs between...

Page 7: ...rk the first line 19 3 4 from the inside of the rear wall Then place more marks 24 on center Repeat process for the opposite sidewall Important When marking the opposite wall place the X mark on the same side of the line so your trusses are parallel when they are installed Check the width in the center of the building The width should be 94 measuring from the outside of the 2x6s 24 19 3 4 ...

Page 8: ...Step 6 Set Trusses Install trusses over the X marks Toenail truss to wall plate using 10d coated nails ...

Page 9: ...ith blue lines together at the peak 1 Install the roof sheathing per the layout below Install the sheathing flush with the 2x4 wall frames not the siding Use 7d sinkers space nails 12 apart 13 x 72 24 x 72 24 x 48 24 x 24 13 x 48 13 x 24 33 x 48 33 x 72 33 x 24 2 Install the 1x3 48 corner trim at the front and rear corner Install trim flush with the siding on the front and back walls Use 7d galv n...

Page 10: ...nges to the door trim temporarily prop the doors in the opening Set the door on a piece of OSB see detail in Step 10 Leave a space between the doors and the side trim to allow room for the doors to expand when they absorb moisture If your door opening is out of square the space around the doors will not be even You can remove and reposition the side trim to make allowances for this The side trim d...

Page 11: ...l ventilation preventing heat and moisture from damaging your building or its contents Optional ridge vent provides ideal ventilation Step 11 Install Roofing Not Supplied in Kit 1 Install metal roof edging perimeter of the roof area Step 10 Install Sliding Door Bolt Back of Left Door Sliding Bolt on the back of left door 1 Install a sliding bolt on the lower back of the door to secure this door in...

Reviews: