Installing additional equipment
76
Fig. 52:
Components of the DR 100 feed unit
4. Connect the base plate (37) and the bottom
of the DR 100 feed unit (33) with washers
and screws.
5. Screw the stand into the stand opening (5)
using an open end wrench. Place the
adapter ring on the stand and tighten the
grub screw.
NOTICE:
The position of the grub screw
determines the swivel radius of the base
plate and is to be set individually.
6. Place the base plate with the DR 100 feed
unit (33) installed on the stand and tighten
it with the toggle screw.
7. Install the vibrating chute and hopper on
the top of the DR 100.
8. Align the vibrating chute (28) over the noise
protection funnel (1.1).
9. Lower the hopper (32) onto the chute (28),
fill in the sample material. Afterwards, lift
the hopper (32) off the chute (28) to
operating height.
The gap should be three times larger than
the largest feed material to prevent
blockage.
Fig. 53:
DR 100 and ZM 300 interface cables
10. Connect the device and the DR 100 feed
unit (33) to the DR 100 interface (17) using
the interface cable supplied (
11. Set the operating switch at the rear of the
DR 100 feed unit (33) to "Standard".
12. Connect the DR 100 feed unit (33) to the
power supply
Fig. 54:
Connection of the DR 100 feed unit
13. Switch on both devices, the DR 100 feed
unit (33) and the ZM 300, with the
respective main switches (16) at the rear of
the devices.
16
17
32
33
28
34
1.1
37