To start-up and commission the Model DXT Demisting Tank, follow these steps:
1) Check and insure that all utilities are properly and securely connected.
2) Ensure that the coalescing filter element is installed and the filter housing cover
properly installed and secured with the spring-loaded latches. Ensure that the
blower discharge pressure bleed valve is in the full closed position.
3) If the DXT is to provide make-up oil to the Oil Mist Generator, fill the reservoir with
quality oil suitable for oil mist lubrication.
WARNING
Maximum DXT reservoir charge volume is 55 US gallons.
Do NOT Overfill.
4) Ensure that the vacuum vent gate valve is in the full open position.
5) Start-up and commission the Oil Mist Generator. See the O&M manual for the Oil
Mist Generator used for start-up instructions.
6) Turn on electrical power, and start the electric blower. Make note of the blower
discharge pressure and temperature. Normally the initial discharge pressure will be
zero, and the discharge temperature will be near ambient. However, as the
coalescing filter element becomes saturated with oil, pressure and temperature will
increase.