1.

  Frame in the enclosure for the unit with framing material. 

  Note: When constructing the framed opening, please ensure there is access to install the gas lines when the unit is installed. 

2.

  For exterior walls, insulate the enclosure to the same degree as the rest of the house; apply vapour barrier and drywall, as per local installation codes. 

(Do not insulate the fireplace itself.)

 

WARNING: Failure to insulate and add vapor barriers to the inside of the exterior wall will result in operational and performance problems 

including, but not limited to: excessive condensation on glass doors, poor flame package, carbon, blue flames etc. These are not product 

related issues.

3.

  The unit does not have to be completely enclosed in a chase. You must maintain clearances from the vent to combustible materials: See "Clearances" 

section.  Combustible materials can be laid against the side and back standoffs and the stove base.

4.

  Tile Finish Option 1: Drywall may be installed onto the unit as shown below to create a surface to apply finishing materials such as tile, slate, etc.  

 

Drywall cannot extend beyond the metal surface of the unit.

5.

  Tile Finish Option 2:  If applying a non-combustible finishing material (tile,slate,etc) the material can be installed directly onto the metal surface (clean 

front) of the unit in the area shown below.

29-7/16"

747mm

21

-3

/8"

[54

2m

m

]

Nailing strip for Tile 

Finish (set back 1/2")

Nailing strip for Clean 

Finish (set flush with 

unit)

TILE FINISH

1.

  There are 8 (eight) side nailing strips and one top nailing strip available on the unit. One set of four (4) are for a clean finish installation, the other set 

are for a tile finish installation as they are set back 1/2" (13mm).  The top nailing strip is adjustable to 1/2" (13mm).

2.

    Bend the required four (4) nailing strips to 90º.

3.

  Attach top nailing strip with one (1) screw (located at the back of the nailing strip). Adjust to required position, flush or back 1/2" and tighten screw.

Nailing strip for Tile 

Finish (set back 1/2")

Nailing strip for Clean 

Finish (set flush with 

unit)

Adjustable Top Nailing 

Strip

Combustible

Material

Non-combustible

Finishing Material

(ie. tile)

Non-combustible Material (3-1/2" x 34-9/16")

Finishing Material

(ie. tile)

Nailing Strip -1/2" back from unit face

Combustible

Material

Non-combustible

Supplied with Unit

1-1/2 (38mm)

Ensure finished

material is

brought to lip

HZ33CE Gas Fireplace

Summary of Contents for HZ33CE

Page 1: ...d Venting Systems Flex Vent Systems FPI AstroCap Flex Vent Rigid Pipe Vent Systems Simpson Direct Vent Pro American Metal Products Amerivent Direct Security Secure Vent Selkirk Direct Temp Metal Fab Sure Seal 34 9 16 16 407mm 23 584mm 878mm 26 1 16 662mm 406mm 16 NAILING STRIP 2 1 2 64mm 742mm 29 1 4 21 3 8 543mm 26 660mm 29 7 16 747mm 742mm 29 1 4 76mm 3 Framing Dimensions Description HZ33CE G Fr...

Page 2: ...ed fires is failure to maintain required clearances air space to combustible materials It is of the greatest importance that this fireplace and vent system be installed only in accordance with these instructions C F G Clearance Dimension Measured From A Front Floor Clearance min 0 Underside of Unit B Sidewall on one side 9 229mm Side Opening of Unit C Ceiling room and or alcove 30 762mm Top Openin...

Page 3: ...eme heat this fireplace emits the mantel clearances are critical Combustible mantel clearances from top of front facing are shown in the diagram on the right Note A non combustible mantel may be installed at a lower height if the framing is made of metal studs covered with a non combustible board Drywall Mantel Clearances 2 0 12 6 4 8 10 2 0 12 6 4 8 10 Top opening of Unit 12 305mm 0 3 1 2 89mm 7 ...

Page 4: ...ll cannot extend beyond the metal surface of the unit 5 Tile Finish Option 2 If applying a non combustible finishing material tile slate etc the material can be installed directly onto the metal surface clean front of the unit in the area shown below 29 7 16 747mm 21 3 8 542mm Nailing strip for Tile Finish set back 1 2 Nailing strip for Clean Finish set flush with unit TILE FINISH 1 There are 8 ei...

Page 5: ...nly to the flanges around the firebox opening Rough edges may be visible from an angle To maintain a clean finished edge facing material edges may be finished with a J style trim or metal cornerbead both materials available at your local building or hardware store IMPORTANT Materials used must be NON COMBUSTIBLE CLEAN FINISH 6 If applying a non combustible facing it may be installed over the metal...

Page 6: ...rtical and offset to vertical terminations using one 90o elbow with rigid pipe vent systems for Propane and Natural Gas Unit must be raised 1 Firestops are required at each floor level and whenever passing through a wall Maintain clearances to combustibles Vent must be supported at offsets Note Must use optional rigid pipe adapter when using rigid vent systems Part 510 994 ...

Page 7: ...and one 90o elbow two 45o elbows equal one 90o elbow Note Must use optional rigid pipe adaptor Part 510 994 when using rigid pipe vent systems Refer Rigid Pipe Venting Systems Section Maintain clearances to combustibles Horizontal vent must be supported every 3 feet Firestops are required at each floor level and whenever passing through a wall A vent guard should be used whenever the terminationis...

Reviews: