10
- Remove the nuts that have been used as standard to secure bearing 2. Replace
them by long nuts 4 and 5 that have been supplied. Nut 4 has been unscrewed
and must fit in plate 3.
- Base plate 18 can be attached to nuts 4 and 5 by using bolts 7 and rings 8.
Simultaneously mount handle 19. NOTE: A left- and a right-hand version has
been supplied of handle 19. The handle must point backwards when mounted.
- Mount plate brake shoe 10 using two bolts 12, two rings 11, two spacers 17 and
two nuts 6 on base plate 18.
- Attach brake spring 16 to both brake shoes 9 and “press/bend” the brake shoes
around the flat side of handle 19 and mounted plate 10.
- Wheel shaft assembly 13 can be slid into bearing 2. Do not forget to secure
conical bushes 23 around the shaft on both sides of bearing 2. NOTE: Ensure
that the splines of shaft 13 match the sprocket wheel. If this is difficult, adjust the
chain tension at a slightly lower value.
- Wheel shaft 13 must not protrude from conical bush 23 on the Verti-Drain
®
side.
The end of shaft 13 must be the same as the end of conical bush 23.
- Check the working of the brake by manually energising handle 19. The handle
should move smoothly. If the brake works correctly, attach brake cable 1 to the
handle using bolt 22, nut 21 and check nut 20.
- Check that all components have been tightened correctly.
- Next, adjust the brake cables in such a way by using nuts 24 that the brake
pedal/parking brake brakes correctly. The brake cables can also be adjusted
under the pedals but making the adjustments at the back wheels is preferable.
- Finally, mount two back wheels 15 using wheel nuts 14 on wheel shaft 13.
- Mount both scrapers. First mount fixing bracket 26 using nut 27 on the back beam
of the Verti-Drain
®
. Next, mount scraper 28 using bolts 29 and nuts 25 to fixing
bracket 26.
3. Mount the front wheel.
4. Check the engine oil.
5. Check the hydraulic oil.
6. Check the machine for damage and loose parts, bolts and nuts.
7. Remove the pallet of the machine.
* Do not crawl under the machine.
* Ensure that the machine is hoisted using solid suspension points to avoid
damage to the machine.
* Ensure that the cable/crane/lift can lift at least 1,000 kg (2205 lbs).
8. Mount the tines.
Fig. 11