All Air From Outside The Building

When installed in a confined space 

without utilizing the intake 

air option

 two permanent openings communicating directly with, 

or by ducts to, the outdoors or spaces that freely communicate with 

the outdoors must be present. The upper opening must be within  

12 in

305 mm

 of, but not less than 

3 in

76 mm

 from, the top of the 

enclosure. The bottom opening must be within 

12 in

305 mm

 of, 

but not less than 

3 in

76 mm

 from, the bottom of the enclosure.

Where directly communicating with the outdoors or communicating 

with the outdoors through vertical ducts, each opening shall have 

a minimum free area of 

1 in

2

/4000 Btu/hr

550 mm

2

/kW

 of 

the total input rating of all of the equipment in the enclosure.
Where communicating with the outdoors through horizontal ducts, 

each opening shall have a minimum free area of 

1 in

2

/2000 Btu/hr

1100 mm

2

/kW

 of the total input rating of all of the equipment in the 

enclosure. When ducts are used, they must have the same cross-

sectional area as the free area of the opening to which they connect.
When calculating the free area necessary to meet the make-up air 

requirements of the enclosure, consideration must be given to the 

blockage effects of louvers, grills and screens. Screens must have a 

minimum mesh size of 

1/4 in

6.4mm

. If the free area through a 

louver or grill is not known, ducts should be sized per Table 3.

Table 3  Make-up Air Louver Sizing

Required Cross Sectional Area

Input

(MBH)

1/4 in 

6.4 mm

Wire Screen

75% Free Area

Metal Louvers

25% Free Area

Wooden Louvers

 

in

2

cm

2

in

2

cm

2

in

2

cm

2

  300

  75

  

484

100

  645

  300    

1935

  400

100

  645

133

  860

  400   

 2581

  600

150

  968

200

1290

  600   

 3871

  750

188

1210

250

1613

  750    

4839

  900

225

1452

300

1935

  900    

5806

1050

263

1694

350

2258

1050

   6774

1350

338

2177

450

2903

1350

   8710

1500

375

2419

500

3226

1500

   9677

1950

488

3145

650

4194

1950

12,581

2100

525

3387

700

4516

2100

13,548

Canadian installations must comply with CSA B149.1 when 

air 

supply

 is provided by natural air flow from the outdoors for 

natural 

draft

, partial fan-assisted, fan-assisted, or power draft-assisted 

burners

, there shall be a permanent air supply opening(s) having  

a cross-sectional area of not less than 

1 in

2

 

per 7,000 Btuh

  

(310 mm

2

 per kW) 

up to

 and including 1 million Btuh

plus

  

1 in

2

 per 14,000 Btuh

 

(155 mm

2

 per kW)

 

in excess of 1 million 

Btuh

Intake Air Option - General Guidelines

This configuration provides combustion air directly to the boiler/

water heater's air intake using a dedicated pipe to obtain combustion 

air from the outdoors. Combustion air can be drawn in horizontally 

through the same outside wall which terminates the exhaust gases or 

vertically through the roof, see Figures 4, 5, 6 & 7.

  Common intake air systems may be used provided 

the common duct is sized properly and an intake 

combustion air damper is installed in the intake air 

pipe of each heater. Improper installation can result in 

excessive levels of carbon monoxide which can cause 

severe personal injury or death!

Single wall galvanized smoke pipe, single wall aluminum pipe or 

flexible aluminum pipe can be used for the intake air pipe. It must be 

sized per Table 4. All joints in metal combustion air systems must be 

secured using corrosion resistant fasteners and sealed using a suitable 

Silicone caulk. 

The combustion air system MUST be supported 

by the building structure not the boiler/water heater.

Table 4  Intake Air Pipe Sizing

Model Size

Pipe Diameter

in 

mm

 

300 & 400

  6 

152

600 & 750

  8 

203

900 & 1050

10 

254

1350 - 2100

12

305

  A stack damper interlocked with the unit should be 

installed in the intake air pipe when the infiltration of 

sub-freezing air could occur, otherwise the unit could 

freeze up voiding the warranty!

Intake Air Option - Horizontal Guidelines

The maximum equivalent length for the horizontal combustion  

air pipe on installations that used the Direct Vent option is 

35 ft

,  

10.8m

. The maximum equivalent length for the horizontal 

combustion air pipe on installations that use the Horizontal Power 

Vent option is 

100 ft

30.5 m

. Each 90° elbow and the combustion 

air terminal are equal to 

10 linear ft

3.0 m

 of pipe. If horizontal  

runs exceed 

5 ft

1.5 m

 they must be supported at 

3 ft

0.9 m

 intervals 

with overhead hangers. The certified combustion air terminal from 

RBI must be used and installed as shown in Figures 4 and 5.

Intake Air Option - Vertical Guidelines

The maximum length for the vertical combustion air pipe is 

30 ft

,  

9.1 m

 plus two 90° elbows. A listed, nonrestrictive combustion air cap 

must be used. The combustion air cap must terminate as shown in 

Figure 6. The penetration point in the roof must be properly flashed 

and sealed.

Summary of Contents for DOMINATOR Series

Page 1: ...ion dust and particulate particularly drywall dust will cause contamination of the burner resulting in possible severe personal injury death or substantial property damage The boiler can only be opera...

Page 2: ...absenceofsuchrequirements totheNationalFuelGasCode ANSI Z223 1 NFPA 54 latest revision Where required by the authority having jurisdiction the installation must conform to the Standard for Controls an...

Page 3: ...ide wall and have adequate fresh air for combustion Ensure that the boiler water heater is level from front to back and from side to side Use metal shims to level the boiler water heater Electrical an...

Page 4: ...Never operate the Dominator in an environment subjected to a negative pressure unless the air intake is connected to the outdoors Failure to comply with this warning can result in excessive levels of...

Page 5: ...rtical Venting using a Masonry Chimney and Inside Air Figure 3 Horizontal Venting using Inside Air 1 5 FT 0 5 m 1 4 IN PER F00T 20 mm m 305 TO 457 127 TO 254 VENT PIPE DIAMETER 5 TO 10 12 TO 18 MINIMU...

Page 6: ...rea of not less than 1 in2 per 7 000 Btuh 310 mm2 per kW up to and including 1 million Btuh plus 1in2 per14 000Btuh 155mm2 perkW inexcessof1million Btuh Intake Air Option General Guidelines This confi...

Page 7: ...t be installed on the same plane outside wall in order to prevent pressure differences due to prevailing winds In cold climates double wall or insulated inlet pipe recommended to prevent condensation...

Page 8: ...and Venting Metal Chimney System Shown Locate exhaust terminal downwind from air intake to reduce potential for flue gas recirculation Figure 7 Combination Air Intake and Venting Masonary Chimney Show...

Page 9: ...To avoid spillage into the room of dangerous flue gas containing carbon monoxide the opening in damper must never face against the flow of flue gas VENT SYSTEM OPTIONS The Dominator may be vented the...

Page 10: ...rate of 1 4 in ft 20 mm m On masonry chimneys the connector must terminate flush with the inside of the chimney flue Figure 2 Fasten each single wall vent connection with at least 3 corrosion resistan...

Page 11: ...ystemmust be pitched down toward the vent terminal 1 4in ft 20 mm m If anypartofasinglewallmetalventsystempassesthroughanunheated space it must be insulated with insulation rated for 400 F 204 C Horiz...

Page 12: ...tl inclinaisonhorizontalequiconviennent ets assurerquelesyst meestexemptd obstruction d tranglement de fruite de corrosion et autres d faillances qui pourraient pr senter des risques c Insofar as is p...

Page 13: ...nal Fuel Gas Code ANSI Z223 1 NFPA 54 et ou des codes d installation CAN CGA B149 GENERAL PIPING REQUIREMENTS Improper piping of this boiler water heater will void themanufacturer swarrantyandcancause...

Page 14: ...1 0 6 400 45 4 0 49 2 9 1 5 600 68 1 1 30 4 3 3 8 750 85 1 2 35 5 4 6 9 900 102 1 3 84 6 4 11 3 1050 119 1 6 23 7 5 18 4 T 20 F T 11 1 C Model Flow Rate Pres Drop Flow Rate Pres Drop Number GPM Ft L s...

Page 15: ...xpansion must be installed in the heating system An expansion tank must be installed close to the boiler on the suction side of the pump An air scoop and automatic air vent must also be installed to e...

Page 16: ...t factory 2 Boiler pump sized to boiler and thermostatic 3 way valve design flow requirements 3 Boiler circuit piping must be sized large enough to handle maximum flow through unit 4 All boilers furni...

Page 17: ...show suggested piping configuration and valving Check with local codes and ordinances for specific requirements Adjustment Procedure To Maintain Inlet Temperature Above Dew Point T1 Temp Min 110 F For...

Page 18: ...ions listed underNORMALinthetable Insomeareasofthecountryadditional precautions must be observed due to unusual characteristics of the local water supply Call the nearest RBI representative for detail...

Page 19: ...Finned copper tube gas boilers water heaters Boiler Manual 19 Table 8A Dominator Heat Exchanger Selection Graph Table 8B Dominator Pumping Performance Requirement...

Page 20: ...temperature pressure relief valve 8 MA Code requires an 1 8 hole in check valve to compensate for thermal expansion Notice These drawings show suggested piping configuration and valving Check with loc...

Page 21: ...pe capacity in ft3 hr based on 0 60 specific gravity gas at a pressure of 0 5 psig or less and a 0 3 WC pressure drop Nominal Iron Pipe Size Pipe length in feet 10 20 30 40 50 60 80 100 150 Maximum ga...

Page 22: ...he instructionscontainedinthismanual Donotattempt to operate this boiler water heater if it has not been installed in accordance with the guidelines set forth in this manual Failure to comply with thi...

Page 23: ...chisusedfor the300andonelowfireandonehighfire pressure switch are used for the 400 through 900 models Two low fireandtwohighfirepressureswitchesareusedforthe1050through 2100 models The low fire pressu...

Page 24: ...normally closed N C contact of K2 1 opens and the normally open N O contact closes The blower changes from low to high speed Prepurge continues 3 The low air indicator will remain on as the blower sp...

Page 25: ...the blower If the side wall vent option is used the power venter is energized closing the powerventerinterlock Thepowerventindicatorlightilluminates 3 The low air indicator light will remain lit unti...

Page 26: ...ignition module The blower will remain on and the low air indicator will remain on for as long as stage 1 remains energized A low air indicator is visible on the control panel OPERATION SEQUENCE 4 ST...

Page 27: ...le on the controller s LCD screen See the staging control documentation for details 2 A powered alarm contact 2A max 24 VAC is available to provide an audio or visual indication of faults related only...

Page 28: ...the control system and any gas control that has been under water N utilisez pas cet appareil s il a t plong dans l eau m me partiellement Faitesinspecterl appareilparuntecnicienqualifi et remplacez t...

Page 29: ...ilot Manifold Settings D300 On Off Only Natural Gas inches W C mm W C Low Fire 1 5 02 33 5 High Fire 2 5 0 2 63 5 LP Gas inches W C mm W C Low Fire 3 9 0 2 99 5 High Fire 9 3 0 2 236 5 Table 20 D300 D...

Page 30: ...than 5 from the rated input value of the unit adjust the manifold pressure accordingly DO NOT adjust the manifold pressure by more than 5 If a properratecannotbemaintainedwithoutadjustingthemanifold p...

Page 31: ...tion or in a drafty area will cause poor or sporadic heating For a thermostat that employs an adjustable heat anticipator adjust the anticipator to match the current measured in the thermostat circuit...

Page 32: ...to properly control the system supply primary loop temperature The firing stages are operated to provide a setpoint temperature in the primary loop SETPOINTOPERATION Thecontroloperatestheboiler water...

Page 33: ...accordance with all applicable localandnationalcodes Improperservicingoradjust ment can damage the boiler water heater Theceramiccombustionchambercontainscrystalline silica Wear a tightly fitted dust...

Page 34: ...ndwashersholdingtheuppercombus tion chamber front panel in place and carefully remove it 9 Carefully slide the heat exchanger out of the unit 10 Remove the V baffle straps and V baffles 11 Thoroughly...

Page 35: ...harge water at normal system pressure If it does contact a qualified service technician to have it inspected NEVER try to clean or repair the relief valve If the valve fails to operate properly have i...

Page 36: ...error message on control refer to control documentation 4 Replace stage control 3 No Power To Pump 1 Pump contact not wired 2 Stage control malfunctioning 3 Pump malfunctioning 1 Wire pump contact to...

Page 37: ...odule 2 Manual valve s closed 3 Low manifold pressure 4 Main valve s malfunctioning 1 Check ground connections adjust as necessary 2 Remove upper front jacket panel open manual valve s 3 Check manifol...

Page 38: ...Finned copper tube gas boilers water heaters Boiler Manual 38 Figure 23 Replacement Parts RIOM 22 REV B REPAIR PARTS...

Page 39: ...e per ft 66 0105 4 4 6 8 10 14 16 16 18 18 PVC Gasket Foam per ft per roll 50 66 0103 50 50 50 50 50 50 50 50 50 50 2 Blanket Insulation per sq ft 05 0200 20 20 22 24 28 30 36 36 44 46 Red Silicone Ga...

Page 40: ...NG 10 0091 5 Main Orifice LP 10 0116 5 NS Pilot Orifice NG 10 0089 1 1 1 1 1 1 1 1 1 Pilot Orifice LP 10 0090 1 1 1 1 1 1 1 1 1 Pilot Orifice NG 10 0093 1 Pilot Orifice LP 10 0094 1 30 Burner Tube 10...

Page 41: ...aders 70 2847 1 70 2848 1 70 2849 1 70 2850 1 70 2851 1 70 2852 1 70 2853 1 70 2854 1 70 2855 1 Individual copper cupronickel tubes available for field repair model and serial number required Tube Exp...

Page 42: ...et Outlet Return Headers ASME 57 0223 12 12 12 12 12 12 12 12 12 12 37 Nut Inlet Outlet Return Headers ASME 57 0492 12 12 12 12 12 12 12 12 12 12 38 Return Header Bronze 01 0018 1 1 1 1 1 1 1 1 1 1 1...

Page 43: ...1 1 1 Harness Kit includes J1 J2 J4 J6 J7 J9 40 0265K 1 1 1 1 1 1 1 1 1 1 J3 RH Side 4 Stage Harness 40 0268 1 1 1 1 1 J5 Blower Vent 4 Stage Harness 40 0271 2 1 1 1 1 J8 Stage Control 2 Stage Harness...

Page 44: ...1 1 1 1 1 1 Flow Switch Outdoor Potter Optional 14 0202 1 1 1 1 1 1 1 1 1 1 NS On Off Switch 48 0010 1 1 1 1 1 1 1 1 1 1 NS 2 Amp Fuse 48 0379 2 2 2 2 2 2 2 2 2 2 NS Rating Plate 82 0054 1 1 1 1 1 1...

Page 45: ...ER SERVICE CLEARANCE PROVIDED IS VENT VERTICAL THROUGH THE ROOF OUTDOOR AIR SENSOR INSTALLED WIRED IS VENT THROUGH THE WALL ARE UNITS RACKED IS POWER VENT INSTALLED AND WIRED IS RACK ASSEMBLED TIGHTLY...

Page 46: ...CSD 1 Pump Delay Combustion Air Damper Power Vent Proving Switch Barometric Damper COMMISSIONING THE UNIT Customer Instructed Yes No All Covers Replaced Yes No Wiring Secure Tight Yes No Customer Give...

Page 47: ...the horizontally vented gas fueled heating appliance or equipment The sign shall read in print size no less than one half 1 2 inch in size GAS VENT DIRECTLY BELOW KEEP CLEAR OF ALL OBSTRUCTIONS g INSP...

Page 48: ...rranty See Installation Instructions for proper pump performance Chemical corrosion no corrosive chemical freon dry cleaning chemicals degreasing liquids chlorine or any chemicals that produce hydroch...

Reviews: