Installation:
POWER SHOULD BE ISOLATED THROUGHOUT THE INSTALLATION PROCESS
Step 1
Secure metal box housing to
wall or secure mounting
position.
The RAK system relies on
being vertically mounted to
allow the ventilation system to
work properly.
Step 2
Bring a separate 10A protected
supply to each RAK case.
Connect the Neutral and Earth
to the buzz bars as shown.
Bring the live to the front of the
metalwork ready for connection
to the circuit board.
Step 3
Bring a single Neutral and Earth
from the buzz bars to the front
of the metalwork.
Prepare screws on either side
of metalwork ready to hold the
circuit board. They should be
present and screwed loosely
into the case.
RAK8-MB
Manual Version 2.1.5