You can edit the following replication settings:
•
To schedule replication jobs, see
.
•
To create a seed drive of a protected machine that is already paired for replication, see
Using the Copy function to create
•
To monitor the progress of a replication job, see
Viewing incoming and outgoing replication
.
•
To pause or resume a paused replication job, see
Pausing and resuming replication
•
To force replication of an incoming or outgoing protected machine, see
•
To manage settings for all target cores and replication procedures, see
Managing settings for outgoing replication
.
•
To manage settings for an individual target core, see
•
priority for a protected machine
.
Parent topic
Scheduling replication
Unless you change the default behavior by setting a replication schedule, the Core starts a replication job
immediately after completion of every backup snapshot, checksum check, attachability check, and the nightly
jobs. For more information, see
.
You can change the replication schedule to reduce the load on the network.
Complete the steps in the following procedure to set a replication schedule for any replicated machine.
1. On the target Core, open the Rapid Recovery Core Console, and from the icon bar, click (Replication).
The Replication page appears.
2. In the Outgoing Replication pane, click to open the drop-down menu next to the Core for which you
want schedule replication, and then select Schedule.
The Replication Schedule for [CoreName] dialog box opens.
3. Select from one of the following three options:
•
At All Times. Replicates after every new snapshot, checksum check, and attachability check, and after the nightly
jobs complete.
•
Daily (Start replication only during the specified time period). Begins replicating only within the time range provided.
1. In the From text box, enter the earliest time at which replication should begin.
2. In the To text box, enter the latest time at which replication should begin.
NOTE:
If replication is in progress when the scheduled time ends, the replication job
completes after the allotted time period.
•
Custom. Begins replicating only within the time range provided, letting you set one time range for weekdays and
another time range for weekends.
1. Next to Weekdays, in the From text box, enter the earliest time at which replication should occur on
a weekday; and then in the To text box, enter the latest time at which replication should occur on a
weekday.
2. Next to Weekends, in the From text box, enter the earliest time at which replication should occur
on weekends; and then in the To text box, enter the latest time at which replication should occur on
weekends.
4. Click Save.